9. Grant of Approval for Authorized Operations.-

 

The Developer shall  submit to the Board the details of operations proposed to be undertaken in the Special Economic Zone  for obtaining authorization under sub-section  (2)  of section 4  at  the time of seeking approval for setting up of Special Economic Zone or thereafter:

 

Provided that exemptions, drawbacks and concessions shall be available for the authorized operations as per the procedure specified in rule 12 after the Special Economic Zone had been notified under rule 8:

 

Provided  further  that  the  Developer  of  an  existing  Special  Economic Zone  shall 1[submit in Form C7 to the Development Commissioner who within a period of fifteen days, shall forward it to the Board with his recommendations] Old[submit to the Board]  the details  of operations  proposed to be undertaken   in   the Special Economic Zone for the purpose of availing exemptions, drawbacks and concessions.

 


1. Substituted vide Notification Dated 14/06/2010