2019(03)LCX0137(AAR)
AAR-GUJARAT
M/s Dholera Industrial City Development Project Ltd
decided on 04/03/2019
GUJARAT AUTHORITY FOR ADVANCE
RULING
GOODS AND SERVICES TAX
A/5, RAJYA KAR BHAVAN, ASHRAM ROAD,
ADVANCE RULING NO. GUJ/GAAR/R/2019/06
(IN APPLICATION NO. Advance Ruling/SGST&CGST/2018/AR/14 & 35)
Date: 04.03.2019
Name and address of the applicant | : |
M/s. Dholera Industrial City Development Project Ltd. Block No.-1/2, Udhyog Bhavan, 6th Floor, Sector-11, Gandhinagar. |
GSTIN of the applicant | : | 24AAFCD5844D1ZW |
Date of application | : | 31.03.2018 |
Clause(s) of Section 97(2) of CGST / GGST Act, 2017, under which the question(s) raised. | : | (b) Applicability of a notification
issued under the provisions of this Act; (d) Admissibility of input tax credit of tax paid or deemed to have been paid; (e) Determination of the liability to pay tax on any goods or services or both; |
Date of Personal Hearing | : | 30.8.2018 |
Present for the applicant | : | CA Amish Khandhar (Consultant) |
2. There are following questions
as per the additional submission dated 12.07.2018 wherein advance ruling is
sought by the applicant, M/s. Dholera Industrial City Development Project ltd. :
1. Whether applicant can claim benefits available to Government Entity?
2. Whether applicant is eligible to claim ITC of GST charged by contractors?
3. Whether applicant is liable to collect GST on amount recovered from
contractors on account of breach of conditions specified in the contract.
4. Whether applicant is liable to collect GST on amount recovered from
contractors on account of not achieving milestone ?
5. Whether applicant is liable to collect GST on interest amount received for
deferring the liquidated damages recovered from contractors?
3. The Applicant has submitted in annexure A of the application, the brief about the company as under :
Delhi Mumbai Industrial Corridor
Government of India has envisaged development of Delhi Mumbai Industrial Corridor ((DMIC) along the alignment of proposed Multi-modal High Axe Load Western Dedicated Freight Corridor (DFC) between Delhi and Mumbai. Further, Delhi Mumbai Industrial Corridor Development Corporation Limited (DMICDC), a special purpose company, was incorporated to establish, promote and facilitate development of the DMIC Project.
Dholera Special Investment Region (DSIR)
Dholera Special Investment Region (DSIR) will be Greenfield Industrial City planned and located approximately 100 KM south of Ahmedabad. The project as envisaged will be the first initiative from DMICDC to create a linear zone of industrial clusters and nodes to be developed in the influence area of Western Dedicated Freight Corridor (DFC). As a new city by 2030, Dholera will cater to a population of 2 million and an employment base of over 8,50,000. This project is considered as dream project of our Prime Minister Shri Narendra bhai Modi.
Government of Gujarat has been proactive in creating suitable legislative framework for formation of a Special Investment Region Act 2009. Under the act, a Regional Development Authority for DSIR has been established in the year 2010. The Dholera Special Investment Region Development Authority (DSIRDA) has the responsibility of planning and development of DSIR and will encompass function of administering government land within DSIR.
Dholera Industrial City Development Limited (DICDL)
For the development of Dholera SIR, the Government of India (through DMIC Trust) and the Government of Gujarat (through DSIRDA) formed a Special Purpose Vehicle (SPV) called Dholera Industrial City Development Ltd.‟ (DICDL) on Jan 28, 2016. The SPV is made up of a 51% stake of the Government of Gujarat through DSIRDA and a 49% stake of Government of India through DMIC Trust.
Dholera Industrial City Development Limited (DICDL‟ or Company‟) is a company registered under Companies Act, 2013 having participation by State Government and Central Government by way of equity in the ratio of 51 percent and 49 percent respectively.
Planning and Development of Dholera Special Investment Region (DSIR)
DSIR has been planned over an extensive area of land measuring approximately 920 Sq. Km. and encompassing 22 villages of Dholera Taluka in the Ahmedabad District. This node is strategically located between the industrial cities of Ahmedabad, Vadodara, Rajkot, Surat and Bhavnagar urban agglomerations. DMIDC, with support of Government of Gujarat, plans to create an economically and socially balanced new-age city with world class infrastructure and highest quality-of-life standards and sustainability in the urban form.
Town Planning Schemes in
DSIR
Government of Gujarat and DSIRDA has adopted the mechanism of town planning
schemes (TP) to ensure delivery of serviced land that can benefit the local
population and the private sector. TP Schemes are being implemented under the
Gujarat Town Planning and Urban Development Act, 1976 (GTPUD). Broadly the TP
mechanism is a means of land pooling for provision of infrastructure. Under TP
schemes, 50% of an individual‟s land holding is aggregated for physical and
social infrastructure, and 50% is returned as serviced land. The 50% land
aggregated for infrastructure is used for roads, physical infrastructure, social
infrastructure and other facilities and amenities. The land which will be used
for common infrastructure is known as public purpose‟ land.
In accordance with GTPUD, for the development of Dholera Industrial City, DICDL has awarded Engineering, Procurement and Construction Contract and it has also awarded certain consultancy contracts as under:
EPC CONTRACTS |
CONSULTANCY CONTRACTS | ||||
Sr. No. | Name of the Contractor | Value of Contract | Sr. No. | Name of the Consultant | Value of Contract |
1 | Cube Construction | 72.31 Cr | 1 | AECOM India Private | - |
2 | Jugalkishor Ramkishan | 14.19 Cr | 2 | Yooshin Enginerring | 25.43 Cr |
3 | Larsen & Turbo Ltd. | 1,734.04 Cr | 3 | Stup Consultant | 14.37 Cr |
4 | Larsen & Turbo Ltd. | 53.91 Cr | 4 | Vyas Gainnetti Creative | 1.64 Cr |
5 | SPML Infra Limited | 90.00 Cr | 5 | Multi Media Consultants | 2.40 Cr |
6 | HCP Design, Planning & | 1.99 Cr | |||
|
Total |
1964.45 |
Total |
45.83 |
Applicant has interpreted the questions raised in the application as per annexure B of application as follows :
As stated in ARA-01, of their submission in respect of the questions raised by applicant in point no.14 and the additional submission dated 12.07.2018, is discussed by applicant below :
Part-A: Applicant i s covered within the definition of Government Identity
General rate of GST on taxable
services is 18%; however, there are several benefits of reduced rate available
to a government entity by virtue of relevant notifications issued by Government.
Notification no. 11/2017-CT (Rate) dated 28.06.2017 provides that certain
construction activity undertaken for Central Government, State Government, Union
Territory, Local Authority, Governmental Authority or Government Entity will
attract GST @ 12%.
Hence, in order to assess whether applicant is eligible to receive such benefits
that a Government Entity is entitled to, the applicant is required to assess the
definition of Government Entity as given under Notification 11/2017-Central Tax
(Rate) dated 28.06.2017:
"An authority or a board or any other body including a society, trust, corporation, i) set up by an Act of Parliament or State Legislature; or ii) established by any Government, with 90 percent or more participation by way of equity or control, to carry out a function entrusted by the Central Government, State Government, Union Territory or a local authority."'
As per the above definition,
Government Entity means any body or corporation
(1) established by any Government;
(2) with 90% or more participation by way of equity or control;
(3) to carry out a function entrusted by the Government.
Further, as per Memorandum of
Association (MoA) of applicant, it is understood that out of total shares of
264.13 Crore, Mr. Alkeshkumar Sharma who is CEO of DMIC i.e. Delhi Mumbai
Industrial Corridor holds 129.42 Crore shares and Mr. Jai Prakash Shivahare who
is nominee of DSIRDA i.e. Dholera Special Investment Regional Development
Authority holds 134.71 Crore shares.
It is to be noted that Mr. Alkeshkumar Sharma who is authorized Central
Government representative holds 49% shares. Besides this, Mr. Jai Prakash
Shivahare who is authorized State Government representative holds 51% shares.
Copy of the shareholding pattern published in MoA is attached herewith for
reference and marked as ˜Annexure “ C of the application.
As per above discussed brief about the company, flow chart and shareholding pattern of applicant discussed above, it is deduced that applicant is formed by Government of Gujarat along with Government of India with a single object to develop Industrial City in Dholera Special Investment Region and Government is having 100% control by way of holding of equity in the company.
Applicant‟s view and understanding:
Hence, in applicant‟s considered view, applicant is very well covered under the definition of Government Entity and it is eligible for benefits that are available to Government Entity under notification no 11/2017-CTR dated 28-06-2017.
Part-B: Applicant can very well avail the Input Tax Credit (ITC) of the Tax paid on the aforesaid contracts:
Summary of GST rate applicable on EPC contracts awarded by the applicant:
Sr. No. |
Name of the Contractor |
Value of Contract | Applicable rate of GST |
1 | Cube Construction Engineering Ltd. “ ABCD | 72.31 Cr | 12% |
2 | Larsen & Toubro Ltd. “ STP | 53.91 Cr | 12% |
3 | SPML Infra Limited “ WTP | 90.00 Cr | 12% |
4 | Larsen & Toubro Ltd. “ R&B | 1,734.04 Cr | 12% |
5 | Jugalkishor Ramkishan Agrawal Infra. Pvt Ltd. “ River Bunding | 14.19 Cr | 12% |
TOTAL | 1964.45 Cr |
Under GST law, taxpayer can claim ITC on inputs and input services used for business p urpose. The definition of input and input services becomes very wide. The said definitions are stated u/s 2(59) & (60) of CGST Act, 2017 and the extract of the same is reproduced below:
"input" means any goods other than capital goods used or intended to be used by a supplier in the course or furtherance of business;
"input service" means any service used or intended to be used by a supplier in the course or furtherance of business;
Now, applicant has availed the
construction, commissioning, installation, repairs, maintenance service from the
various contractors stated in Part-B above. The said services are availed by
applicant in course or furtherance of business.
Now, the activity clause stated in MoU of applicant is reproduced below:
To carry on the business of planning, development, operations and management of integrated industrial township including industrial townships, residential townships, vocational training centers, leisure parks, conventional centers and development of other infrastructure facilities and to act as technical consultants and advisors in all matters relating to integrated industrial township development. Further, to undertake, identify, formulate, design, develop, structure, engage in project development, project financing, project monitoring, establishment, strengthening, up gradation, repair, rehabilitation, improvement operation, construction, maintenance, management and implementation of the integrated industrial township for the Dholera Special Investment Region, Gujarat, whether whole of the project or any components, and its support facilities to further the aforementioned objectives amongst others to conceive, identify, formulate, initiate, promote, aid, design, establish, operate, manage, construct, erect, maintain, regulate, rehabilitate, repair, improve and participate and develop this project and to finance and/or arrange for financing of the above activities and collecting, retaining and appropriating tariffs, charges, tolls, fees, prices, rents and all types of revenues, cess, user development fee (including internal as well as external development charges), accept receivables towards dues, investments, returns, servicing/ repayments of debts or capital etc. and to carry out any other project development and implantation activities as may be necessary, and incidental for implementation of the Project. And for these purposes to procure, implement, operate and maintain schemes, project(s), programmes, concessions and other contractual arrangements on a commercial format, in public private sector partnership mode or otherwise, for the provision and development of projects related to power generation, transmission and distribution, water treatment and supply, waste management, sewage treatment, sanitation, roads, transportation, logistics parks, exhibition cum convention centers, street lighting, city gas supply along with supporting amenities that will essentially include residential clusters, educational clusters, research, commercial, recreation, offices & administration uses and to further the aforementioned objectives. Also to carry out all kinds of business of developers, promoters, consultants, designers, manufacturers, processors, assemblers, agents, system designers, dealers, contractors, builders, engineers, distributors, marketing, materials, personnel, planning, management, dealers for erection and commissioning of all types of infrastructure and all other works, facilities, services, systems, methods, erections and things of any description whatsoever as the Company thinks proper for facilitating, developing, establishing and improving the project.
Based on the aforesaid
detailed scope of activity includes construction service as well.
Now, Sec: 17(5) of CGST Act, 2017 provides the list of
blocked credit where the service recipient can‟t avail the credit of Tax paid on
input service. Relevant extract of clause (c) and (d) of Section 17(5) of CGST
Act, 2017 is reproduced below:
(c) works contract services when supplied for construction of an immovable property (other than plant and machinery) except where it is an input service for further supply of works contract service;
(d) goods or services or both received by a taxable person for construction of an immovable property (other than plant or machinery) on his own account including when such goods or services or both are used in the course or furtherance of business.
Applicant‟s view and understanding:
As per applicants‟s understanding of Section 17 (5) of CGST Act, it is submitted that if service recipient i.e. the applicant is also in the same line of business [provider of works contract services] then, only credit of the Tax paid on works contract service will be available. Furthermore, as per clause (d), ITC of goods or services received by taxable person is eligible only if such goods or services are received for construction of an immovable property.
In the instant case, applicant
will also get itself engaged in same line of business and the said fact is
clearly stated in object clause of MoU. Formation of Applicant is done by
Governments [Central as well as State] for the sole purpose of development of
entire Dholera City. And for such development of city, the applicant will engage
itself in construction of various commercial as well as residential complexes.
Such complexes will be sold to the person intending to be part of Dholera
Industrial City. For development of entire city, certain basic infrastructure
facility like roads and administration building are required to be developed.
Further, Dholera being a industrial city, major Sewage Treatment Plant and Water
treatment plant are also basic necessity for smooth operations of entire city.
Various contracts awarded to the contractor is for developing infrastructure
facilities in the entire city and as per MoU, applicant is getting these
infrastructure facilities developed so that further development of commercial
and residential complex can be undertaken by the applicant.
Hence, it is can be said that the services received by applicant from above
mentioned contractor is for further development of the Dholera City and such
development will be undertaken by applicant in future after the basic
infrastructure facilities are in place. Therefore, it is submitted that
applicant can very well avail the ITC of Tax paid on composite works contract
service availed from contractors stated in Part B.
Applicant is entered with Cube
Construction Engineering Limited is for Design and Construction of
Administration and Business Center of Dholera for design and construction of
Administration and Business Centre of Dholera (ABCD) Building, maintenance of
project and fulfillment of other obligation. Administrative & Business Centre
for Dholera (ABCD Building) is envisaged to function as a centre for
administering & overseeing the development works of DSIR. DSIRDA and by DICDL
along with other stakeholders being local development authority will pursue
administrative, manage and monitor the developmental activities of DSIR. It is
cleared that above building is used for administration activity of applicant and
so that applicant can very well avail the ITC of service received from cube
construction limited.
Applicant is in the business of developing the township and for which it is going to provide the service of construct, erect, maintain, regulate, rehabilitate, repair, improve and development of township. Here the contract entered with Larsen and Toubro Ltd is for Road building and Sewage treatment plant. Road building is most necessary and basic requirement for development of any township. Sewage treatment plant is for the process of removing contaminants from wastewater, primarily from household and industrial sewage. Physical, chemical, and biological processes are used to remove contaminants and produce treated wastewater (or treated effluent) that is safer for the township. So from the above explanation it is clearly deduced that service received from Larsen and Toubro limited is eligible for the availment of ITC by applicant.
Similarly, contract entered with SPML Infra Limited is for design, engineering, supply, erection and testing of water treatment plant on turnkey basis. Water treatment is any process that improves the quality of water to make it more acceptable for a specific end-use. The end use may be drinking, industrial water supply, irrigation, river flow maintenance, water recreation or many other uses, including being safely returned to the township. Hence, it is deduced that it would also be an input for the maintenance of township. It is cleared from the explanation that applicant is very well eligible to avail the ITC of service received from SPML Infra Limited.
Contract entered with Jugalkishor
Ramkishan Agrawal Infra. Pvt Ltd is for Adhiya river bunding. The Adhiya river
(Tributary of sukhbhadar river) originates at village Cher and meets the
Sukhbhadar river near village Khoon. Adhiya river and Sukhbhadar river do not
have well defined banks and also pass through flat topography so flood water
spills over the area and slowly flows into sea. Hence, for development and
safety of township water flow of river must required to be controlled. River
bunding project is necessary input for the expansion of Dholera project and
according to that we are eligible to avail the ITC of works contract service
received from Jugalkishor Ramkishan Agrawal Infra. Pvt Ltd.
Applicant‟s view on taxability on amount collected from contractors on account
of violation charges, liquidation damages and interest on liquidation damages
are as follows :
As per the agreement with various
contractors, applicant aims to build an image of the best safety conscious
practice in DSIR construction and operation undertaken by contractors. An unsafe
act or conduct in the construction site may result into an illness, injury,
property damage or worst, loss of life. The contractor is expected to take
safety very seriously and shall keep the construction site safe at all the
times. The Employer shall practice zero tolerance towards unsafe behavior by any
parties on the construction site.
There is table provided in the agreement indicates the safety, health and
environment violation (unsafe act / unsafe condition) and charges to be
recovered from contractors. Copy of sample agreement where the said violation
charges are mentioned is attached herewith and marked as
Now, the question comes whether
said violation charges which are adjusted from the payment of the contractors is
liable to GST or not. It is noted that said violation charges are not collected
separately by the applicant; however the same is adjusted from the payments made
to contractors.
To check the GST applicability, we need to refer the definition of supply and
confirm that whether the aforesaid transaction entered by applicant falls under
supply or not. The word supply‟ has been expressed u/s 7 of CGST Act, 2017.
Relevant extract of the said Section is reproduced below:
"supply" includes all forms of supply of goods or services or both such as sale, transfer, barter, exchange, licence, rental, lease or disposal made or agreed to be made for a consideration by a person in the course or furtherance of business;
Now, as per section 2(31) of
CGST Act, 2017
"consideration" in relation to the supply of goods or services or both
includes““
(a) any payment made or to be made, whether in money or otherwise, in respect
of, in response to, or for the inducement of, the supply of goods or services or
both, whether by the recipient or by any other person but shall not include any
subsidy given by the Central Government or a State Government;
(b) the monetary value of any act or forbearance, in respect of, in response to,
or for the inducement of, the supply of goods or services or both, whether by
the recipient or by any other person but shall not include any subsidy given by
the Central Government or a State Government:
Provided that a deposit given in respect of the supply of goods or services or both shall not be considered as payment made for such supply unless the supplier applies such deposit as consideration for the said supply;
From the above legal proposition it is deduced that to treat as supply‟ following conditions must be fulfilled:
i. There should be an activity
i.e. sale, barter, transfer etc.
ii. Consideration must be received to service provider.
iii. The said activity must be made by person in course of furtherance of
business.
Now, the word activity has not defined in GST law. Normally, an activity would include an act done, a work done, a deed done, an operation carried out, execution of an act, provision of a facility etc. Where applicant receives the violation charges from contractors there is no activity done by both the parties. Means there is no activity undertaken by contractor while paying violation charges and hence first condition has not fulfilled.
Further, there is no quid pro
quo‟ i.e. something in return received by contractors. The payment made by
contractor doesn‟t fall within the definition of consideration‟ and hence
second condition has also not fulfilled.
As per Sec: 15 of CGST Act, 2017, interest or late fee or penalty for delayed
payment of any consideration for any supply received shall be included in the
transaction value of supply. However, the said violation charges are not in the
form of penalty for delayed payment and hence need not to include in the value
of supply of services provided by contractors.
In nutshell, the aforesaid
transaction undertaken between applicant and contractors is not covered under
definition of supply‟ and hence no GST shall be leviable on the amount received
by applicant from various contractors in relation to violation charges related
to safety and health of workers.
Applicant has entered into contracts with various contractors on a turnkey basis
for construction of Road and buildings, water treatment plants, sewage treatment
plants, admin building and many future projects. As per the contract the
milestone and time of completion are well defined and where there is delay in
completion of a particular stage as defined under contract then there is a
separate clause for Liquidated Damages which is described in detail as under:
(1) In the event that
the contractor fails to achieve any project milestone or the scheduled
completion date within a period of 30 days from the date set forth in
schedule-J, Contractor shall pay damages to the employer of a sum calculated at
the rate of 0.05% of the contract price for delay of each day reckoned from the
date specified in schedule-J and until such project milestone is achieved or the
works are completed; provided that if the period for any or all project
milestones or the scheduled completion date is extended in accordance with the
provisions of this agreement,
(2) The dates set forth in schedule-J shall deemed to be modified accordingly
and provision of this agreement shall apply as if schedule- J has been amended
as above;
(3) In the event the works completed within or before scheduled completion date
including any time extension, applicable for that work or section, damages paid
under this clause 10.3.2 shall be refunded by employer to the contractor but
without any interest thereon. (ANNEXURE-E of the application)
Hence, as per the above contract clause on Liquidated
Damages, it can be deduced as under:
(1) In case of delay in achieving milestone by the contractor, contractor is
liable to pay damages @ 0.05% of the contract price for delay days.
(2) However, where the work is completed within or before scheduled completion
date then damages paid by contractor will be refunded back to the contractor.
This situation can be understood by way of following illustration wherein the
contract value is Rs. 100 Crore.
For E.g. Milestones are defined as under:
1st Stage of Completion : 10% of
work to be done upto 31st March 2018
2nd Stage of Completion : further 10% of work to be done upto 30th June 2018 So
on and so forth.
Hence, in example specified above, the contractor is required to complete 20% of total project by 30th June 2018.
(a) Now, say, the contractor
could not complete 10% of work till 31st March 2018 and contractor could manage
to finish 10% of work on 10th April 2018. Delaying the project by 10 days.
In this Scenario, although damages of Rs. 5,00,000/- per day is required to be
paid by contractor to the applicant [Rs. 100 Crore * 0.05% = Rs. 5,00,000/-].
Contractor will be liable to pay Rs. 50,00,000/- [Rs. 5,00,000/- * 10 Days]
(b) Now, the contractor was able to accelerate and finish 20% of work till 30th
June 2018.
Hence, 20% of work was completed
within given milestone. According to the contractual terms, applicant will have
to refund back the amount of Rs. 50,00,000/-.
There is one more clause in para no 10.3.2, the agreement with regards to the
damages which is reproduced as under:
―For the avoidance of doubt, it is agreed that recovery of Damages under this clause 10.3.2 shall be without prejudice to the rights of the Employer under this Agreement including the right of Termination thereof.‖
As per the above clause, the
applicant reserves the right to terminate the right to recover the damages from
contractors. It is further submitted that board of directors of the applicant in
board meeting held on 11/11/2016 resolved that in event of 78% excessive
rainfall during this period, the board after deliberation decided to defer the
imposition of such damages but it is clarified that interest on such deferment
will be charged and levied from 1st day of default.
In the case of applicant there is contingency occurred for the payment of LD
charges. It is clear from the extract of contract clause that LD would be charge
on non-achievement of milestone but if in future milestone achieved and project
gets well in time then applicant is required to refund the amount of LD.
Accordingly, applicant has been
entered with an arrangement that they were defer the receipt of LD, means they
are not going to charge the LD from contractors and they will wait for them
until they achieve their next milestone. Additionally, for this arrangement,
they will charge the interest amount from the contractors for the period
occurred between two milestone.
As per section 15(1) of CGST Act,2017
The value of a supply of goods or services or both shall be the transaction value, which is the price actually paid or payable for the said supply of goods or services or both where the supplier and the recipient of the supply are not related and the price is the sole consideration for the supply.
In the case of applicant, there
is not any supply involved as there is not any amount deducted from RA Bill and
Tax invoice has also not been issued by applicant for receiving any amount
towards the damages due to not achieving the milestone.
Hence, it is very well clear that there is not any supply involved in the above
transaction.
Ruling by Maharashtra Authority for Advance Ruling in case of Maharashtra State Power Generation Company Limited
Recently Maharashtra Authority for Advance Ruling has issued an order dated 08.05.2018 regarding GST applicability on liquidated damages in case of construction of new power plants or renovation of old plants. Bench has issued an order that GST would be applicable on liquidated damages.
Following are the facts of case decided in Maharashtra Authority for Advance Ruling:
1. The contractor shall strictly adhere to the project completion schedule to achieve the trial operation of the units by specified time period. In case the contractor fails to achieve successful completion of Trial operation within specified time period as pe the project completion schedule due to delay in his part, then the owner shall levy liquidated damages.
2. If the contractor fails to achieve the trial operation of the unit within the time period specified in the project completion schedule due to reasons attributable to him then the owner shall levy liquidated damages on the contractor @ 1.2% of the contract price for erection, testing and commissioning along with applicable price variation per week of delay or part subject to maximum 10% of contract value.
It is submitted that there is
difference in facts of the case of applicant as compared with the fact of the
case stated in the Maharashtra Authority for Advance Ruling and the case of
applicant.
As per the illustration discussed above, the applicant is contractually
obligated to refund the amount of damages collected in event of the contractor
achieving the milestone subsequently.
The applicant has been entered with the clause of liquidated damages for delayed completion of contracts by various contractors. The contractors shall construct the project works in accordance with the project completion schedule set forth in schedule-J of the agreement. In the event that the contractor fails to achieve any project milestone or the scheduled completion date within a period of 30 days from the date set forth in schedule-J, unless such failure has occurred due to force majeure or for reasons solely attributable to the employer, it shall pay damages to the employer of a sum calculated at the rate of 0.05% of the contract price for delay of each day reckoned from the date specified in schedule-J and until such project milestone is achieved or the works are completed; provided that if the period for any or all project milestones or the scheduled completion date is extended in accordance with the provisions of this agreement, the dates set forth in schedule-J shall deemed to be modified accordingly and provision of this agreement shall apply as if schedule-J has been amended as above; provided further that in the event the works completed within or before scheduled completion date including any time extension, applicable for that work or section, damages paid under this clause 10.3.2 shall be refunded by employer to the contractor but without any interest thereon.
As the outcome of Board Meeting
of applicant dated 11/11/2016, it was resolved to defer the liquidated damages
payable by the contractor, however the interest at the applicable rate due to
delay in the achievement of 1st milestone will be recovered from the contractors
as provided for in the contract.
There is specific clause that if the next milestone will be achieved in time
then applicant is required to refund the amount of liquidated damages collected.
As this is contingent obligation of contractor, instead of receiving and
refunding the amount of damages applicant is just charging the interest on that
amount. This arrangement is just for time value of money.
Clause of liquidated damages extracted from the agreement and Board Meeting
resolution has been provided in ANNEXURE-E and ANNEXURE-F, of the application,
respectively.
As explanation provided in the
Part D, amount recovered from contractors for not achieving milestone is not a
supply as per section 15(1) of CGST Act,2017. As the transaction of damages is
not falling within the definition of supply, Section 15(2)(d) will also not
apply regarding inclusion of interest amount in the value of supply.
So it is very well clear that as the charges for late achieving milestone is not
an supply, interest on such supply is also not an supply.
On other hand interest
income is clearly exempted from the GST law. According to notification no
12/2017 Central Tax (Rate)
Services by way of”
(a) extending deposits, loans or advances in so far as the consideration is represented by way of interest or discount (other than interest involved in credit card services);
"interest" means interest payable in any manner in respect of any moneys borrowed or debt incurred (including a deposit, claim or other similar right or obligation) but does not include any service fee or other charge in respect of the moneys borrowed or debt incurred or in respect of any credit facility which has not been utilised;
Above arrangement entered by an
applicant is just like advance credit given to the contractors and for that
amount applicant is charging interest thereon. It is just an amount which is
receivable by applicant for the period starting from 1st milestone to the end of
next milestone but the applicant is not receiving the amount from contractors
but charging the interest on that much of amount which they are differing.
Hence, from the above it is very much clear that this is just an interest income
on granting the use of money to the contractors and it is clearly exempt from
the GST as per the above clarification. So as per the above explanations
interest income on that charges is clearly exempt from GST Law.
Applicant has concluded in the following table:
Part | Question | Applicants View |
A | Whether applicant is covered within definition of Government Entity? |
Yes, the applicant is covered within the definition of Government entity‟. |
B | Whether applicant is eligible to claim ITC of GST charged by contractors? |
Yes, applicant is eligible to claim ITC on Tax paid for works contract service availed from various contractors. |
C | Whether violation charges collected from contractors is liable to GST or not? |
No, as the said transaction doesn‟t fall within the ambit of supply‟ and hence no GST shall be leviable on the said payment. |
D | Whether applicant is liable to collect GST on liquidated damages recovered from contractors on account of not achieving milestone? |
No, as the said transaction doesn‟t fall within the ambit of supply‟ and hence no GST shall be leviable on the said payment. |
E |
Whether applicant is liable to collect GST on interest amount received for liquidated damages recovered from contractors for not achieving milestone? |
¢ No, as the main
transaction doesn‟t fall within the ambit of supply‟ and hence no GST
shall be leviable on the interest received on that charges. |
4. The application was sent to
the jurisdictional CGST commissionerate for its opinion. They have, inter alia
opined, vide their letter dtd. 30.05.2018 as follows:
(a) Whether applicant is covered within definition of Government Entity‟?
For the development of Dholera Special Industrial Region, Dholera Industrial
City Development Ltd. has been formed by the Government of India (51% stake of
the State Government and 49% stake of the Government of India). Government
Entity has been defined in Notification No.31/2017-Central Tax (Rate) dated
13.11.2017, which reads as:-
"Government Entity" means an authority or a board or any other body including a society, trust, corporation, i) set up by an Act of Parliament or State Legislature; or ii) established by any Government, with 90 per cent. or more participation by way of equity or control, to carry out a function entrusted by the Central Government, State Government, Union Territory or a local authority."
From the Government of Gujarat, Industries & Mines Department‟s letter dated 02.12.2015 (attached as Annexure-C of the application), it is clear that the State Government has formed a Company under the name Dholera Industrial Township Development Limited as a wholly owned government Company with (51%) equity contribution of Government of Gujarat in the form of land and (49%) Central Government through Delhi-Mumbai Industrial Corridor (DMIC) Project Implementation Trust Fund as a Project Development Agency for Dholera Special Investment Region. From the above definition, it appears that the applicant is a Government entity.
(b) Whether applicant is eligible
to claim ITC of GST charged by contractors?
Clause (c) of Section-17(5) of CGST Act, 2017 provides the eligibility of input
tax credit in case of works contract service where it is an input service for
further supply of works contract service. Considering the extent of business of
construction & erection, maintenance, repair to be conducted by the applicant,
the eligibility for input tax credit can only be decided after ensuring that the
further supply of works contract service is made by the applicant on a case to
case basis.
(c) Whether applicant is liable to collect GST on amount recovered from contractors on account of breach of conditions specified in the contract?
The applicant has contended that they would adjust the violation charges against the payable amount to the contractor. The applicant can reduce his tax liability only if the contractor has reduced the input tax credit claimed by the same amount. Thus, it follows that the principle of unjust enrichment or reduction in output tax liability of the applicant will not be allowed if the incidence of tax has been passed on to another person.
5. Discussion and findings:
Following are the questions submitted by the applicant for advance ruling:
(i) Whether applicant can claim
benefits available to Government Entity?
(ii) Whether applicant is eligible to claim ITC of GST charged by contractors?
(iii) Whether applicant is liable to collect GST on amount recovered from
contractors on account of breach of conditions specified in the contract.
(iv) Whether applicant is liable to collect GST on amount recovered from
contractors on account of not achieving milestone ?
(v) Whether applicant is liable to collect GST on interest amount received for
deferring the liquidated damages recovered from contractors?
Now we take up the queries for
discussion one by one as follows:
(i) Whether applicant can claim benefits available to Government Entity?
Government entity has been defined in Notification No.11/2017- Central Tax
(rate) dated 28.06.2017, as amended, which reads as below:-
Government Entity‖ means an authority or a board or any other body including a society, trust, corporation, i) set up by an Act or Parliament or State Legislature,; or ii) established by any Government, with 90 per cent. or more participation by way of equity or control, to carry out a function entrusted by the Central Government, State Government, Union Territory or a local authority.
Since the applicant is constituted by the participation share of 51% of State Government and 49% of Central Government, hence being, fully constituted by the share of Government, the applicant is covered under the definition of Government Entity
(ii) Whether applicant is
eligible to claim ITC of GST charged by contractors?:
Clause (c) of Section 17(5) of CGST Act, 2017 provides the eligibility of input
tax credit in case of works contract service where it is an input service for
further supply of works contract service. Considering the extent of business of
construction & erection, maintenance, repair to be conducted by the applicant,
the eligibility of input tax credit can only be decided after ensuring that the
further supply of works contract service is made by the applicant on a case to
case basis.
(iii) Whether applicant is liable to collect GST on amount recovered from contractors on account of breach of conditions specified in the contract ? :
We find that Clause (e) of Para 5 of Schedule II of the Central Goods and Services Tax Act, 2017 provides that the following activity be treated a supply of services:
"(e) agreeing to the obligation to refrain from an act, or to tolerate an act or a situation, or to do an act;"
As per the above provision, the transaction shall be treated as supply of services. Moreover, as violation charges are payable by the contractors, the same are required to be treated as consideration. Therefore, this transaction is liable to GST.
(iv) Whether applicant is liable
to collect GST on amount recovered from contractors on account of not achieving
milestone ?
We find that Clause (e) of Para 5 of Schedule II of the Central Goods and
Services Tax Act, 2017 provides the following activity to be treated a supply of
services:
"(e) agreeing to the obligation
to refrain from an act, or to tolerate an act or a situation, or to do an act;
and" As per the above provision, the transaction shall be treated as supply of
services. Moreover, liquidated damages are payable by the contractors,
therefore, the same are to be treated as consideration. Therefore, this
transaction is liable to GST.
The Advance Ruling of Maharashtra Advance Ruling Authority in the case of
Maharashtra State Power Generation Co. Ltd. No.GST-ARA-15/2017-18/B-30 Dated
8/5/2018 is also in consonance with the present ruling.
(v) Whether applicant is liable to collect GST on interest amount received for deferring the liquidated damages recovered from contractors?:
We find that, as ruled above,
liquidated damages are liable to tax and interest on liquidated damages is a
part of liquidated damages, therefore the interest is also liable to tax.
6. In view of the above, in respect of application of M/s. Dholera
Industrial City Development Project ltd., we rule as under:
R U L I N G
Question-1: Whether applicant can
claim benefits available to Government Entity?
Ans: Answered in affirmative.
Question-2: Whether applicant is
eligible to claim ITC of GST charged by contractors?
Ans: Clause (c) of Section-17(5) of CGST Act, 2017 and GGST Act, 2017 provides
the eligibility of input tax credit in case of works contract service where it
is an input service for further supply of works contract service. Considering
the extent of business of construction & erection, maintenance, repair to be
conducted by the applicant, the eligibility for input tax credit can only be
decided after ensuring that the further supply of works contract service is made
by the applicant on a case to case basis.
Question-3: Whether applicant is
liable to collect GST on amount recovered from contractors on account of breach
of conditions specified in the contract.
Ans: Answered in affirmative.
Question-4 : Whether applicant is
liable to collect GST on amount recovered from contractors on account of not
achieving milestone ?
Ans: Answered in affirmative.
Question-5 : Whether applicant is
liable to collect GST on interest amount received for deferring the liquidated
damages recovered from contractors?
Ans: Answered in affirmative.
(R.B. Mankodi)
Member
(G.C. Jain)
Member
Place: Ahmedabad
Date: 04.03.2019.