2018(07)LCX0133(AAR)
AAR-MAHARASHTRA
M/S North american coal CORPORATION INDIA PRIVATE LIMITED
decided on 11/07/2018
MAHARASHTRA AUTHORITY FOR
ADVANCE RULING
(Constituted under section 96 of the Maharashtra Goods and Services
Tax Act, 2017)
BEFORE THE BENCH OF
(1) SHRI B.V. BORHADE Addl.
Commissioner of Central Tax, (Member)
(2) SHRI PANKAJ KUMAR Joint Commissioner of State Tax,( Member)
GSTIN Number, if any/ User-id | ||
Legal Name of Applicant | M/S North american coal CORPORATION INDIA PRIVATE LIMITED | |
Registered
Address/Address provided while obtaining user id
Correspondence Address |
||
Application | ||
Jurisdictional officer | ||
Nature of activity(s) (proposed / present) in respect of which advance ruling sought | ||
A | Category | |
B | Description (in brief) | |
Issue/s on which advance ruling required | ||
Question (s) on which advance ruling is required |
PROCEEDINGS
(Under Section 98 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017)
No.- GST-ARA-07/2018-19/B-63
Date : July 11, 2018
The present application has been
filed under section 97 of the Central Goods and Services Tax Act, 2017 and the
Maharashtra Goods and Services Tax Act, 2017 [hereinafter referred to as the CGST Act and MGST Act] by M/s. North american
coal Corporation India Private limited, the applicant, (hereinafter also
referred to as, NACC) seeking an
advance ruling in respect of the following question.
1. Whether liquidated damages that may be awarded to the Applicant by the
International Chamber of Commerce (ICC) qualifies as a supply under the Goods
and Services Tax (GST) law, thereby attracting the levy of GST?
2. If the answer to Question No. 1 is in the affirmative, what should be the
time of supply, that is to say, the point of time in which NACCs liability to
pay GST arises ?
3. If the answer to Question No. 1 is in the affirmative, what should be the
value of supply on which GST is payable, that is to say, whether the Applicant
is liable to pay GST on amount of liquidated damages claimed and awarded to the
Applicant under the arbitral award or the amount which is actually received by
the Applicant after conclusion of the matter before the final Appellate
authority.
At the outset, we would like to make it clear that the provisions of both the
CGST Act and the GST Act are the same except for certain provisions. Therefore,
unless a mention is specifically made to such dissimilar provisions, a reference
to the CGST Act would also mean a reference to the same provision under the MGST
Act. Further to the earlier, henceforth for the purposes of this Advance Ruling,
a reference to such a similar provision under the CGST Act / MGST Act would be
mentioned as being under the GST Act.
02. FACTS AND CONTENTION - AS PER THE APPLICANT
The submission (Brief facts of the case), as reproduced verbatim, could be seen
thus -
I. Statement of the relevant facts having a bearing on the advance ruling sought
by the Applicant
1. The Applicant, North american coal Corporation India Private Limited (NACC
India) is a private limited company incorporated under the provisions of the
Companies Act, 1956 having its registered office at 1st Floor, Deepgriha, S.No.
50/1/2, Chhaya Society, Bhakti Marg, Off Law College Road, Erandavane, Pune -
411004, India. NACC India has been incorporated to carry on the business of
providing technical consultancy relating to coal mining and related activities.
2. The Applicant is a wholly owned subsidiary of the North American Coal
Corporation, USA (NACC US). NACC US is a company formed under the laws of the
State of Delaware, United States of America. NACC US is engaged in surface
mining of lignite as fuel for power generation by electric utilities.
3. Sasan Power Limited (SPL or Reliance) is a company incorporated under the
provisions of the Companies Act, 1956, having its registered office in Mumbai.
It is a wholly owned subsidiary of Reliance Power Limited and is a part of the
Reliance Anil Dhirubhai Ambani Group. It carries on the business of developing,
designing, operating maintaining and owning an Ultra Mega Power Project in Sasan,
Madhya Pradesh, India.
4. NACC US has entered into an Association Agreement for mine development and
operations (Association Agreement with SPL effective January 1, 2009 (Refer
Annexure A) in order to provide technical know-how to SPL in relation to mine
development and operations. The technical know-how, generally identified as
evaluation of geological data preparation of feasibility study, development of
annual mining and life of mine plans, mine planning design, assistance in
training the SPL personnel, monitoring and reviewing, training to employees,
providing NACCs practices related to operating procedure, health and safety for
mining operations etc. The Association Agreement defind the
roles/responsibilities of both the parties, scope of work, fees structure,
periodicity, manner of payment, As per the Association Agreement, specific
payment for off-shore services was to be made to NACC US on a quarterly basis
and expenses pertaining to the onsite services were to be reimbursed separately.
The off-shore services for mining operations consisting of geological, mining,
environmental, and seismic and overall mine management methodology were provided
by expert teams from the United States of America.
5. The Association Agreement was first amended vide the First amendment to
Association Agreement dated September 30, 2009 for amending the payment
mechanics thereunder (Refer Annexure B).
6. Subsequently, in March 2011, NACC US incorporated a subsidiary, NACC India,
being the Applicant, and through the Assignment and Assumption Agreement,
Consent, and Second Amendment to the Association Agreement dated April 1, 2011
(Refer Annexure C), the rights and obligations of NACC US as per the original
Association Agreement were transferred and assigned to the Applicant, with the
consent of SPL.
7. Further, the Applicant has entered into an Intellectual Property License and
US Service Agreement (IP & Services Agreement) with NACC US dated 1st April
2011 (Refer Annexure D), for receiving services and a non-exclusive license of
Intellectual Right from NACC US. The terms of the IP & Services Agreement
includes the following scope for the years under consideration:
Grant by NACC US to the Applicant of non-exclusive, non-transferable, non
assignable, non-sub licensable license to use the Licensed Intellectual property
in India in connection with the Applicants provision of mining services to SPL
and any other customer in India.
Provision of US based services by NACC US to Applicant that will assist the
Applicant in performing its obligations to SPL.
8. As per the Association Agreement, the Sasan Project was divided into three
phases as detailed below depending on the stage of development of the mine
(i) Pre-Development Phase included the preliminary offsite activities ranging
from preliminary data collection and evaluation, development of mine plans to
the provision of bidding support and representation for mine plan approval.
This phase broadly covered the period from August 2007 to March 2009. As per the
Association Agreement, SPL was required to pay a pre-development phase fee of
USD 75,000 per quarter for each calendar quarter in the period from 01 January
2008 through 01 January 2009.
(ii) Development Phase - The development phase included on-site and offsite
activities viz. implementation of mine plans and designs prepared during the
pre-development phase, defining equipment specification, mine equipment vendor
selection and monitoring, mine plan modifications to suit on-ground
requirements, regular troubleshooting etc. This phase broadly covered the period
from April 2009 and was expected to continue till December 2014. The Development
phase would continue to the first date following a period of thirty consecutive
days during which the annualized rate of coal production at the Sasan mine has
equalled the rate of seven million tonnes per year for such thirty days. As per
the Association Agreement, SPL was required to pay a development phase fee USD
250,000 per quarter for each calendar quarter after the Pre-Development phase.
(iii) Production Phase - The production phase pertains to the period of
production of coal and includes the postproduction on-site and offsite
activities viz. regular recommendations relating to mining operations;
monitoring and review of mine operations; preparation of policies and
recommending systems for mining operations, equipment maintenance and
environmental compliance; audit of mining operations. This phase would broadly
cover the period from January 2015 till December 2027 (the estimated life of the
mine) and will commence following a period of thirty consecutive days once the
annualized rate of coal production at the Sasan mine has equalled the rate of
seven million tonnes per year for such thirty days. As per the Association
Agreement, SPL was required to pay a production phase royalty of an amount
equivalent to higher of a) USD 250,000 per annum or b) USD 0.1125 for each ton
of coal produced from the mine each quarter.
9. In terms of the Association Agreement, SPL was obligated to remunerate NACC
US/Applicant in the following manner:
Section 5.4 Automatic Payments/Invoicing.
(a) Pre-Effective Date U.S. Services. Within five (5) days after the Effective
Date, NAC shall invoice Reliance for (i) any unpaid amounts described in Section
5.7 (a) that were incurred prior to the Effective Date and (ii) the amount
described in Section 5.1(b). The invoice shall be accompanied by reasonable
supporting documentation in respect of any unpaid amounts described in Section
5.1(a). Payment by Reliance shall be due within thirty (30) days of Reliances
receipt of such invoice.
(b) Post-Effective Date Services. Within fifteen (15) days after the end of each
calendar quarter, NAC shall invoice Reliance for (i) the amounts described in
Section 5.1 (a) and (ii) the amounts described in Section 5.2 that were incurred
during such quarter (and after the Effective Date). The invoice shall be
accompanied by reasonable supporting documentation. Payment shall be due within
thirty (30) days of Reliances receipt of such invoice.
(c) Development Phase Fee. Each quarterly installment of Development Phase Fee,
together with the Gross-Up Payment, shall be due on the forty-fifth (45th) day
of each quarter during the Development Phase. NAC shall invoice Reliance for the
U.S. Dollar amount of the applicable Development Phase Fee and the estimated
Cross-Up Payment not later than the first (1st) day of the quarter for which the
Development Phase Fee is due.
(d) Production Phase Royalty. Within Five (5) days after the end of each quarter
during the Production Phase, Reliance shall provide NAC with written
documentation reasonably evidencing the number of Tonnes of coal produced from
the Mine during such quarter within ten (10) days after NAC receives such
written documentation, it shall invoice Reliance for the U.S. Dollar amount of
the production Phase Royalty on the basis of such receipts, together with the
estimated Gross-Up Payment. Payment of the invoice amount shall be due within
thirty (30) days of Reliances receipt of such invoice.
10. NACC US, in the initial phase of mine development and later the Applicant,
rendered significant services to SPL under the above mentioned agreements which
contributed immensely to the progress of the project in Sasan. However, SPL
cortailed the activities of the Applicant and engaged its in-house international
consultants. The last invoice paid by SPL pertained to the period up to
September 2013 and it stopped making payment of invoices of the Applicant
pertaining to services performed after the period October 1, 2013. The total
unpaid invoices raised on SPL are detailed below:
Invoice No. |
Invoice Description |
Invoice Date |
Terms |
Due Date |
Amount USD |
Amount INR |
2013/14-008 | Q4 2013 Dev. Fee | 01-Oct-13 | 45 days | 15-Nov-13 | 311,046.27 | |
2013/14-011 | Q1 2014 Dev. Fee | 02-Jan-14 | 16-Feb-14 | 311,046.27 | ||
2013/14-012 | Q4 2013 exp. | 16-Jan-14 | 30 days | 15-Feb-14 | 5,032,790 | |
2014/15-001 | Q2 2014 Dev. Fee | 0l-Apr-14 | 45 days | 16-May-14 | 315,602.34 | |
2014/15-002 | Q1 2014 exp. | 11-Apr-14 | 30 days | 11-May-14 | 6,628,189 | |
2014/15-003 | Q1 2014 exp. | 11-Apr-14 | 30 days | 11-May-14 | 71,235.97 | |
2014/15-004 | Interest | 23-May-14 | Receipt | 23-May-14 | 44,320.42 | |
2014/15-005 | Interest | 23-May-14 | Receipt | 23-May-14 | 212,646 | |
2014/15-007 | Interest | 01-Ju1-14 | Receipt | 0l-Jul-14 | 14,626.54 | |
2014/15-008 | Interest | 0l-Jul-14 | Receipt | 0l-Jul-14 | 169,050 | |
2014/15-009 | Q2 2014 exp. | 10-Jul-14 | Receipt | 10-Jul-14 | 4,949,343 | |
2014/15-010 | Q2 2014 exp. | 10-Jul-14 | Receipt | 10-Jul-14 | 104,303.95 | |
2014/15-11 | Interest | 23-Jul-14 | Receipt | 23-Jul-14 | 8,227.81 | |
2014/15-12 | Interest | 23-Jul-14 | Receipt | 23-Jul-14 | 95,095 | |
2014/15-13 | Q3 2014 Dev Fee upto July 23, 2014 | 23-Jul-14 | Receipt | 23-Jul-14 | 78,900.59 | |
Total Amounts due | 1,259,310.16 | 17,087,113 |
11. The Applicant has
charged Service tax on the invoices raised by it for the services rendered under
the Association agreement and has also duly deposited the same with the
Government exchequer even for the invoices where the payment has not been
received from SPL.
12. In compliance with the procedures set out in the Association Agreement, the
Applicant repeatedly expressed serious concerns over non-payment of
aforementioned invoices. Despite several written and in person requests from the
Applicant, SPL did not honour its obligations under the agreement and therefore,
the Applicant was constrained to terminate the Association Agreement with SPL.
In this regard, the relevant Articles of the Association Agreement are
reproduced below:
ARTICLE VI
TERM AND TERMINATION
Section 6.1 Term. Under earlier terminated in accordance with Section 6.2, the
term of this Agreement shall commence on the Effective Date an shall continue
until the end of the Production Phase (the Initial Term). Following the
Initial Term, the parties may extend this Agreement by written agreement for any
number of one (1) year terms (each, an Extended Term and, together with the
Initial Term, the Term) until the Agreement is terminated pursuant to Section
6.2.
Section 6.2 Termination. This Agreement may be terminated :
a) At any time by mutual agreement of the parties;
b) By either parties in accordance with Article VII (Force Majeure); or
c) By either parties in accordance with Article VIII (Events of Default).
Section 6.3 Effect of Termination
(a) Upon termination of this Agreement for any reason, NAC shall furnish to
Reliance (a) within sixty (60) days after the effective date of termination, an
initial invoice for settlement of all costs incurred prior to the termination
date and (b) within twenty (20) days of incurring such costs, additional
invoices for (i) the On-Site Costs incurred as a result of the repatriation of
the On-Site Consultants and (ii) the On-Site Costs relating to the
tax-equalization payments for the On-Site Consultants. Reliances payments of
such invoices shall be subject to the provisions of Sections 5.3 and 5.6.
(b) If Reliance terminates this Agreement pursuant to Section 6.2(c), any
damages recoverable by Reliance shall be limited to the amount of the
Development Fees and/or Production Phase Royalties actually paid by Reliance
during the year in which Reliance terminates this Agreement pursuant to Section
6.2(c), in no extent to exceed U.S. $ 1,000,000 in the aggregate.
(c) If NAC terminates this Agreement pursuant to Section 6.2(c), Reliance shall
pay to NAC, as liquidated damages and not as a penalty or other punitive amount,
the amount specified below:
If Termination Occurs During: Then the Termination Payment is U.S.: Year 1 of
the Development Phase $11 million Year 2 of the Development Phase $13 million
Year 3 of the Development Phase $15 million Year 4 or later of the Development
$17 million phase Any year in the production phase $17 million, less the
aggregate amount of the Production Phase Royalties received by NAC prior to the
termination date
ARTICLE VIII
EVENTS OF DEFAULT
Section 8.1 Default by Reliance. If Reliance shall at any time be in breach of
its (a) payment obligations, (b) other obligations pursuant to this Agreement,
including failure to provide reasonable access to the Mine, the Preparation
Plant or any Mining Project that are relevant to the duties and obligations of
NAC hereunder and the failure to timely provide presentations in section 13.2(1,
NAC may give written notice of such default to Reliance, in which caseReliance
shall have twenty-one (21) days within which to cure the default. If, at the end
of the twenty-one (21) day period, Reliance has not cured the default NAC shall
have the right, (i) if the default is of the type described in subclause (a)
above, to immediately cease providing the Services until such time as the event
of default is cured, (ii) if the default is of the type described in subclause
(b) above, to cease providing such Services as NAC determines, in its reasonable
discretion, cannot be performed due to Reliance's default until such time as the
event of default is cured, or (iii) if any such default is not cured within
sixty (60) days and NAC is not then in breach of this Agreement, to terminate
this Agreement. Reliance shall continue to be responsible for the On-Site Costs
during the period of the default and prior to the termination of the Agreement.
Section 8.2 Default by NAC. If NAC shall at any time be in breach of its
obligation to provide Services hereunder, Reliance may give written notice of
such default to NAC, in which case NAC shall have ten (10) days within which to
cure the default. If, at the end of the ten (10) day period, NAC has not cured
the default Reliance shall have the right (i) to cease reimbursing NAC for
Services not actually provided until such time as the event of default is cured
or (ii) if the default is not cured within sixty (60) days and Reliance is not
then in breach of this Agreement, to terminate this Agreement. Reliance shall
not be responsible for the On-Site Costs during the period of default and prior
to the termination of this Agreement, other than the repatriation and tax
equalization costs identified in Annex C and, if any, on the On-Site Consultants
Schedule
13. On May 23, 2014, the Applicant served notice on SPL in accordance with
Section 14.1 of the Association agreement for an event of default as defined in
Section 8.1 for failure by SPL to make payments as required under Article 5 of
the Association Agreement. The notice of default provided SPL with 21 days to
cure the default as stipulated in the aforesaid agreement.
14. 0n June 13, 2014, after 21 days lapsed without SPL curing its payment
default, the Applicant became entitled to cease provision of services to SPL
pursuant to Section 8.1 and the same was done by way of correspondence dated
June 19, 2014. The Applicant continued to engage in a good faith dialogue to
enable SPL to cure its default and avoid termination of agreement. However, SPL
failed to make the due payments and continued the default.
15. Following the completion of 60 days from the notice of default, the
Applicant sent a notice for termination of the Association Agreement on July 23,
2014 for continued breach of the terms of the aforesaid Agreement for SPL's
failure to pay the Applicant for services it performed for the period after
October 1, 2013 in terms of default mentioned in section 8.1 (a) of Article VIII
of the Association Agreement.
16. The termination affected by the Applicant under the terms of Association
Agreement resulted in the Applicant claiming from SPL the past due and amounting
to USD 1,259,310 for development fee and INR 17,087,113 for reimbursement of
expenses (including interest thereon) and of liquidated damages to the tune of
USD 17 million as per Section 6.3 of the Association Agreement. A copy of the
said notice for termination of the Association Agreement is attached as Annexure
E.
17.Upon SPL's refusal to pay the aforesaid claims due to Applicant under the
Association Agreement, the Applicant filed a request for arbitration on August
8, 2014 with the International Chamber of Commerce (ICC) in London pursuant to
the dispute resolution terms/procedure set out in section 12.2 of the
Association Agreement. The relevant section of the Association Agreement is
reproduced below
Section 12.2 Dispute Resolution: Arbitration
(a) Any and all claims, disputes, questions or controversies involving Reliance
on the one hand and NAC on the other hand arising out of or in connection with
this Agreement (collectively, Disputes) which cannot be finally resolved by
such parties within 60 (sixty) days of arising by amicable negotiation shall be
resolved by final and binding arbitration to be administered by the
International Chamber of Commerce (the ICC) in accordance with its commercial
arbitration rules then in effect (the Rules''). The place of arbitration shall
be London, England. Each party shall appoint one (1) arbitrator and the two (2)
arbitrators so appointed shall together select and appoint a third arbitrator.
If either Reliance, on the one hand, or NAC, on the other hand, fail to appoint
their respective arbitrator within thirty (30) days after receipt by
respondent(s) of the demand for arbitration or if the two (2) parly-appointed
arbitrators are unable to appoint the chairperson of the arbitral tribunal
within thirty (30) days of the appointment of the second arbitrator, then the
ICC shall appoint such arbitrator or the chairperson, as the case may be, in
accordance with the listing, ranking and striking provisions of the rules. Save
and except the provision under Section 9, the provisions of the Part 7 of
(Indian) Arbitration and Conciliation Act, 7 996, as amended (the Arbitration
Act) shall not apply to the arbitration. The arbitrators shall not award
punitive, exemplary, multiple or consequential damages. In connection with the
arbitration proceedings, the parties hereby agree to cooperate in good faith
with each other and the arbitral tribunal and to use their respective best
efforts to respond promptly to any reasonable discovery demand made by such
party and the arbitral tribunal.
(b) All arbitration proceedings shall be conducted in the English language and
the arbitral award (the Award) shall be rendered no later than six (6) months
from the commencement of the arbitration or as otherwise provided by the Rules,
unless otherwise extended by the arbitral tribunal for no more than an
additional six (6) months for reasons that are just and equitable.
(c) Except as otherwise required by Applicable Laws of India, the arbitration
proceedings and the Award shall not be made public without the joint consent of
each party and each party shall maintain the confidentiality of such proceedings
and the Award.
(d) Each party shall bear its own arbitration expenses and Reliance on the one
hand, and NAC, on the other hand, shall pay one-half of the ICCs and the
chairperson's fees and expenses, unless the arbitrators determine that it would
be equitable if all or a portion of the prevailing party's expenses should be
borne by the other party. Unless the Award provides for nonmonetary remedies,
any such Award shall be made and shall be promptly payable in (i) U.S. Dollars
if payable to NAC or (ii) Rupees if paid to Reliance net of any tax or other
deduction. The Award shall include interest from the date of any breach or other
violation of this Agreement and the rate of such interest shall be specified by
the arbitral tribunal and shall be calculated from the date of any such breach
or other violation to the date when the Award is paid in full.
(e) All notices and other communications by any party to the other party or by
the arbitral tribunal to any disputing party in connection with the arbitration
hereunder shall be in accordance with the provisions of Section 14.1.
(f) Each of the Parties expressly understands and agrees that the Award shall be
the final and binding remedy between them regarding any and all Disputes
presented to the arbitral tribunal.
18. The ICC had accepted jurisdiction on August 11, 2014 and, at the request of
the Applicant and NACC US, which had instituted a separate arbitration
proceeding against SPL, consolidated the two arbitrations into one arbitration
proceeding on March 12, 2015.
19. Thereafter, SPL filed a civil suit against the Applicant in the District
Court in Singrauli at Waidhan contending that both the parties to the dispute,
SPL and the Applicant, being companies incorporated under the Companies Act,
1956 in India, cannot participate in the arbitration proceedings which have seat
of arbitration outside India. The Singrauli District Court granted an ad-interim
ex-parte injunction restraining the Applicant from proceeding any further with
the arbitration proceedings before ICC in London. The Applicant got a relief
from the Hon'ble Madhya Pradesh High Court vide order dated March 9, 2015
directing the Singrauli District Court to dispose of the suit filed by SPL.
Pursuant to the order of the Hon'ble Madhya Pradesh High Court, the Singrauli
District Court passed an order dated March 19, 2015 vacating the ad-interim
injunction.
20. SPL filed an appeal against the order of the Singrauli District Court dated
March 19,2015 before the Hon'ble Madhya Pradesh High Court. The Hon'ble Court
delivered its final order on September 11, 2015 dismissing the appeal of SPL by
holding that when the parties have agreed to resolve all their disputes by
arbitration, they cannot be permitted to avoid arbitration.
21. Aggrieved by the order of the Madhya Pradesh High Court, SPL filed a Special
Leave Petition (SLP) on September 19, 2015 before the Hon'ble Supreme Court of
India against the above mentioned judgement of the Hon'ble Madhya Pradesh High
Court which is pending disposal.
22. By way of Order dated August 24, 2016, the Hon'ble Supreme Court disposed of
the SLP filed by SPL by ruling that the parties can participate in arbitration
proceedings outside India despite being companies incorporated under Companies
Act, 1956, in India.
23. Pursuant to the aforesaid Order of the Hon'ble Supreme Court, the parties
have initiated the arbitration proceedings before ICC. ICC has fixed the date of
hearing in the matter from 3 April 2018 to 8 April 2018.
24. The Applicant mentions that, when the Applicant had approached the Hon'ble
Authority for Advance Ruling (Authority) that functioned under the erstwhile
service tax regime, the Authority had rejected the Application of the Applicant
vide its Ruling dated 6 May 2017 observing, inter alia, as follows:
The question of whether or not the Applicant ought to pay service tax on
liquidated damages is not liable to be entertained as it is not certain today
whether the liquidated damages would be granted at all in the arbitration
proceedings.
The question posed to Authority is not a valid question since it depends on
uncertain event of the Applicant succeeding in arbitration proceedings.
It may happen that after the Authority gives its ruling, the Applicant may
eventually fail in its attempt to earn liquidated damages.
In view of the uncertainty of the event, it would not give a finding on an event
that had not occurred as yet.
A copy of the Ruling dated 6 May 2016 of the Authority is annexed herewith as
Annexure F.
25. The Applicant humbly submits that the above order of the Authority should
not, in any manner, whatsoever, stand in Applicant's way of approaching your
good self yet again as there is no bar prescribed in this regard under the GST
law and the questions posed by the Applicant in the instant application
qualifies as questions in respect of which an advance ruling can be sought by
the Applicant under the CGST Act, 2017 in terms of Section 97(2) of the Act.
26. Further, the Applicant being a wholly owned subsidiary of a foreign holding
company is eligible to approach this Hon'ble Authority for an advance ruling and
qualifies as an applicant under Secrion 97 of the Central Goods and Services Tax
Act, 2017 (hereinafter referred to as the CGST Act).
27. The Applicant submits that there are no pending proceedings against the
Applicant or initiated by the Applicant in relation to the questions raised
herein before any authority, Tribunal or Court.
Additional Submissions for NACC India Private Limited on 13.07.2018
1. Under the GST law, all supplies of goods and services attract GST and section
9 of the CGST Act, 2017 is the charging section. The said section provides that
there shall be a levy of a tax called the central goods and services tax on all
intra-state supplies of goods or services or both on the value determined under
section 15 of the CGST Act, 2017.
2. In this regard, section 7 of the CGST Act, 2017 defines the term 'supply' and
the relevant portion of the same is reproduced hereunder as follows for the sake
of brevity:
7. (1) For the purposes of this Act, the expression supply includes
(a) all forms of supply of goods or services or both such as sale, transfer,
barter, exchange, license, rental, lease or disposal made or agreed to be made
for a consideration by a person in the course or furtherance of business;
(b) import of services for a consideration whether or not in the course or
furtherance of business,
(c) the activities specified in Schedule 1, made or agreed to be made without a
consideration; and
(d) the activities to be treated as supply of goods or supply of services as
referred to in Schedule II.
3. Section 7 of the CGST Act, 2017 defines the term 'supply' to include all
forms of supply of goods or services or both and it expressly seeks to include
all activities treated as supply of goods or supply of services as referred to
schedule II of the CGST Act, 2017. In this regard, clause 5(e) provides that
agreeing to the obligation to refrain from an act, or to tolerate act or a
situation, or to act shall be treated as a supply of services. The relevant
portion in Sch II is as below:
SCHEDULE II
(Section 7)
5. Supply of services
The following shall be treated as supply of services, namely:-
(a) ...........
(b)..............
(e) Agreeing to the obligation to refrain from an act, or to tolerate an act or
a situation, or to do an act; and
4. Detailed submissions in respect of the aforesaid are presented below.
Applicant's obligation under the Association Agreement doesn't constitute as
supply of service:
5. As submitted in its application, the Applicant would like to reiterate that
the claim of liquidated damages doesn't qualify as a 'service' itself, as it
lacks the element of reciprocity which forms sine qua non for a transaction to
qualify as a service. Therefore, there is no question of the claim of liquidated
damages leading to any 'supply of service.'
6. Without prejudice to the aforesaid, even if one were to argue that the claim
of liquidated damages amounts to a 'service', such claim cannot be regarded as
being in the course or furtherance of business. The termination of the
Association Agreement puts an end to the business of the relationship of the
Applicant with the service recipient. It results in complete and absolute
cessation of the business of the Applicant and not its furtherance. All the
obligations of the Applicant qua the service recipient under the Association to
exist once the Association Agreement is terminated and the same cannot be said
to be in furtherance of the Applicant's business. Also, the act of termination
cannot be called 'in course of any business as the usage of the term 'in course'
indicates the continuity of an activity. When the Applicant terminates the
Association Agreement, there is no continuation of any business of the Applicant
with the service recipient as all obligations under the Association Agreement
cease to exist. In the light of the above, the damages claimed for such
termination can, therefore, not be regarded as being in the course or
furtherance of business. Therefore, such claim cannot be regarded as being
towards 'supply of any service'.
7. The Ld. Sales Tax Officer appears to be of the view that liquidated damages
claimed for nonperformance of a contract gets covered under Clause 5(e) of
Schedule II to the CGST Act, 2017. The Applicant doesn't agree with such
interpretation of the Ld. Sales Tax Officer. The Applicant's submissions in this
regard are detailed below.
Conditions for levy of GST under Clause 5(e) of Schedule II
8. To qualify as a 'supply of services' as envisaged under clause 5(e) of
Schedule II appended to the CGST Act, 2017, the following conditions ought to be
satisfied:
There should be agreement between parties towards discharging a
contractual/agreement-linked obligation by the supplier of service;
The obligation should be to either 'refrain from an act' or to 'tolerate an act
or a situation':
The obligation should be discharged in lieu of certain consideration.
9. In order to examine the provisions under Clause 5(e) of Schedule II to the
CGST Act, 2017, it should first be relevant to understand as to what should
qualify as an Obligation
10. GST law does not contain any definition of the term Obligation. Therefore,
it would be relevant to examine the definition of the said term under other
legislations/ judicial pronouncements and understand its dictionary meaning.
11. The term Obligation has been defined under Section 2(a) of the Specific
Relief Act, 1963 as follows:
2. Definitions.
(a) Obligation includes every duty enforceable by law;
12. The Andhra Pradesh High Court in case of Hyderabad Stock Exchange Ltd vs
Rangnath Rathi & CO (AIR (1958) AP 431 has held that 'An obligation is a tie or
a bond which constraints a person to do or suffer something'.
13. As per the Black's law dictionary, the term Obligation has been defined
as:
A legal or a moral duty to do or not do something.
14. As per Wharton's law lexicon, the term Obligation has been defined as:
An act, which binds a person to some performance; or for the performance of a
covenant etc.
15. From conjoint reading of the previously mentioned definitions, it is clear
that an Obligation is imposition of duty to perform an agreed act or a
covenant, which is enforceable under law
16. The occurrence of the term 'obligation' under Clause 5(e) of Schedule II of
the CGST Act, 2017, mandates that the tolerance must be of an act or a situation
and such tolerance must be enforceable.
17. Based on the terms of the Association Agreement, it is clear that the
Obligation on part of the Applicant is to provide technological know-how to
the service recipient based in India. There is no other obligation on the
Applicant per se apart from provision of technological knowhow to the service
recipient based in India,
18. The obligation to provide technological know-how is the only obligation
enforceable under the Association Agreement by the service recipient. Service
recipient's failure to discharge its obligations under the Association Agreement
gives the Applicant a right/entitlement to terminate the Association Agreement.
There is no obligation on the Applicant to terminate the Association Agreement.
Also, there is no consideration assigned for any obligation to terminate it.
19. The intention of the contracting parties emanating from the Association
Agreement clearly indicates that the Applicant intends to supply and the
recipient intends to receive technical know-how. There is nothing whatsoever in
the Association Agreement that indicates that the intention of the contracting
parties is really to effect a breach of the contract, which is to be tolerated
by the either of them.
20. It is critical to note that there is no clause in the Association Agreement
that obligates the Applicant to tolerate the act of default on part of the
service recipient, and continue to supply services despite such default.
21. On the contrary, Section 6.2. (c) read with Section 8.1 the Association
Agreement provides that the Applicant has a right to determine the contract upon
occurrence of any of the specified Events of Default. In fact, upon occurrence
of a specified event of Default, the Applicant has actually terminated the
Association Agreement. Therefore, any obligation under the contract ceases
thereafter for the Applicant.
22. In the instant case, when the Applicant had terminated the Association
Agreement, it was relieved from its entire obligations thereunder to supply
services to the service recipient. The claim of liquidated damages is an act
subsequent to the act of termination of the Association Agreement.
23. Had there been any tolerance of an act or a situation by the Applicant in
the instant case when the service recipient default in making payments, the
Applicant would have continued to provide its services despite a default by the
service recipient. The Applicant would not have terminated the Association
Agreement had there been any tolerance on its part. The Applicant terminated the
Association Agreement and sought liquidated damages only because there is no
tolerance on its part of the breach effected by the service recipient.
Liquidated Damages received for breach/termination of contract cannot qualify as
'consideration'
30. Under the GST law, the term consideration has been defined under Section
2(31) of the Central Goods Service Tax Act, 2017, as follows:
(31). consideration in relation to the supply of goods or services or both
includes ,-
(a) any payment made or to be made, whether in money or otherwise, in respect
of, in response to, or for the inducement of, the supply of goods or services or
both, whether by the recipient or by any other person but shall not include any
subsidy given by the Central Government or a State Government;
(b) the monetary value of any act or forbearance, in respect of, in response to,
or for the inducement of, the supply of goods or services or both, whether by
the recipient or by any other person but shall not include any subsidy given by
the Central Government or a State Government:
Provided that a deposit given in respect of the supply of goods or services or
both shall not be considered as payment made for such supply unless the supplier
applies such deposit as consideration for the said supply;
31. From the definition of the term 'consideration', it is apparent that
consideration can be monetary or non-monetary and that same should be 'in
respect of, 'in response to', 'or for the inducement of the supply of goods or
services or both, meaning thereby that it should be identified with a supply of
service and have nexus with the said supply of service
32. The Applicant submits that liquidated damages paid by the service recipient
is neither in 'in respect of 'nor 'in response to any supply made by the
Applicant. Instead, it is paid to make good the loss/ injury suffered by the
Applicant as a result of the premature termination of the Association Agreement
entered into between the Applicant an the service recipient. It is submitted
that the liquidated damages in the instant case cannot be regarded as
consideration for any provision of service as payments made on early termination
by the lessor because of a lessee's default cannot qualify as consideration as
the payments made i) are damages for the loss suffered by the Applicant and ii)
have no nexus with any identified supply. The payment of liquidated damages by
the service recipient is made as a consequence of a breach leading to
termination and is not a fee or remuneration for any obligation or tolerance
undertaken by the Applicant.
33. The nature of damages claimed on termination of a contract was examined by
the Apex Court in Maharashtra State Electricity Distribution Company v. Datar
Switchgear Limited & Others, (2018) 3 SCC133. The principle laid down by the
Court is that the injured party should be placed as good a situation as if the
contract had been performed. In other words, it is to provide to damages for
pecuniary loss, which naturally flows from the breach. The Court placed its
reliance on an earlier decision of the Apex Court in Union of India v. Sugauli
Sugar Works (P) Ltd v., (1976) 3 SCC 32: Once it is established that the party
was justified in terminating the contract on account of fundamental breach
thereof, then the said innocent party is entitled to claim damages for the
entire contract i.e.for the part which is performed and also for the part of the
contract which it was prevented from performing.
34. Under the service tax law, which had identical requirements, it was settled
law that mere flow of money cannot be subject matter of service tax and
consideration/money should have 'nexus' with an identified supply of service. It
was also equally settled that payment for damages made were not for any
provision of service and were instead were made to make good the loss suffered.
Reference is invited by the Applicant to the following case laws:
In the case of Cricket Club of India v. Commissioner of Service Tax [(2015) (40)
STR 973], the Hon'ble CESTAT (Mumbai Bench), observed as under:
11.................... Consideration is undoubtedly, an essential ingredient of
all economic transactions and it is certainly consideration that forms the basis
for computation of service tax. However, existence of consideration cannot be
presumed in every money flow. The factual matrix of the existence of a monetary
flow combined with convergence of two entities for such flow cannot be moulded
by tax authorities into a taxable event without identifying the specific
activity that links the provider to the recipient.
12. Unless the existence of provision of a service can be established, the
question of taxing an attendant monetary transaction will not arise.
Contributions for the discharge of liabilities or for meeting common expenses of
a group of persons aggregating for identified common objectivities will not meet
the criteria of taxation under Finance Act, 1994 in the absence of identifiable
service that benefits an identified individual or individuals who make the
contribution in return for the benefit so derived.
13. .............Neither can monetary contribution of
the individuals that is not attributable to an identifiable activity be deemed
to be a consideration that is liable to be taxed merely because club or
association is the recipient of that contribution.
(Emphasis supplied)
Mormugao Port Trust v.
Commissioner of Customs, Central Excise and Service Tax, Goa; 2016 TIOL 2843
CESTAT Mum, highlighting the importance of nexus of a service with the element
of consideration to render a transaction liable for service tax, the Hon'ble
Jurisdictional CEST AT (Mumbai) observed as follows:
18. In our view, in order to render a transaction liable for service tax, the
nexus between the consideration agreed and the services activity to be
undertaken should be direct and clear. Unless, it can be established that a
specific amount has been agreed upon as a quid pro quo for undertaking any
particular activity by a partner, it cannot be assumed that there was a
consideration agreed upon for any specific activity so as to constitute a
service.
In a JaipurJewellery Show v. CCE & ST, jaipur-1, 2017 (49) STR 313 (TRI),
dealing with service tax liability on cancellation charges the Hon'ble Tribunal
held as follows:
6 .......... that the same are being retained, as regards the cancellation
charges, we note by the appellant from the initial amounts given to them for
booking a booth, when the same is subsequently cancelled by the customer and the
amount is refunded to them. Admitted position, which emerges is, that no booths
are ultimately rented out by the appellant to their customers. As explained,
such cancellation charges are for putting the appellant into inconvenience by
initially booking the booths and subsequently cancelled. Inasmuch as no service
stand provided by the appellant to their customers and for which purpose no
consideration was ever received by them, we are of the view that the
cancellation charges recovered by the appellant cannot be held to be the
Consideration for providing business exhibition services. The same are thus not
liable to service tax,
In Reliance Life Insurance Company Ltd. v. Commissioner of Service Tax, Mumbai
ll, Appeal No. ST/85584/2015, the Hon'ble Mumbai Tribunal had dealt with the
question of payment of service tax on surrender or partial withdrawal charges
under the category of 'Management of Investment under ULIP services' for the
period 01.04.2009 to 30.06.2012. These charges were collected by the assessee
when a policy holder dilutes the policy completely or partially and had no nexus
with the provision of main service of management of funds. In these
circumstances, the Hon'ble Mumbai Tribunal held that there cannot be any levy of
service on the surrender and partial withdrawal charges collected by the
assessee as such charges i) cannot be considered as charges towards provision of
services of management of an investment, ii) are in the nature of penalty or
liquidated damages and iii) ULIP is primarily a contract between the insurer and
the insured and when seen in the context of sections 73 and 74 of the Indian
Contract Act, 1972, surrender of policy is nothing but ending of contract for
which damages are paid and the same cannot be termed as charges towards
management. In the words of the Hon'ble Tribunal:
.............The fact which emerges from the above shows that the charges are
either in the nature of 'penalty' or liquidated damages or a combination of
both. Thus in no way it can be considered as charges towards providing of any
services of management of investment under Unit Linked Insurance Plan ....... We
find that ULIP is primarily a contract between the insurer and insured and thus
when seen in the context of Section 73 and 74 of the Contract Act, 1872 what
transpires is that surrender of policy is nothing but ending of contract for
which compensation in the form of damages which cannot be termed as charges
towards management.
In view of our above discussion and on perusal of the facts of the case we are
of the view that the surrender charges are not part of taxable service of
management of funds. Rather it is in the nature of penalty of liquidated damages
which is not a service and hence cannot be made liable for tax during the period
involved..
35. Further, it is important to keep in mind that the sum received by the
Applicant is liquidated damages for the loss suffered by it as a result of
premature termination of the contract. Recovery and payment of liquidated
damages is a post termination event having no connection with the main supply of
provision of technical know-how. Since the Applicant is wronged by the service
recipient's default in performing its obligations under the contract, liquidated
damages is recovered by the Applicant to make goods the loss suffered by it and
the said amount, it is re-iterated is not towards provision of any service.
36. On application of the above definitions and the above case laws to the
Applicant's case, it is submitted that the flow of money from the service
recipient is not for any provision of supply of service of tolerating any
default in payment by the service recipient.
37. Instead, the claim of liquidated damages is against the loss suffered by the
Applicant on account of the default committed by the service recipient. Any
payment received as genuine damages or loss flowing from early termination as a
result of a default one party, can not be regarded as a consideration for a
supply. Therefore, it is submitted that there can be no taxable supply in the
instant case as the payment for genuine damages is no consideration for any
earlier or current supply.
38. The submission of the Applicant that damages received by it is not
consideration for any supply is also substantiated from the following foreign
case laws dealing with similar issues and having provisions with identical
language:
In GSTR 2003-2011, the Australian Taxation Office (ATO) had to consider the
applicability of GST on payments made on an early termination of a lease of
goods by a lessor on account of a lessee's default. Under the Australian GST
law, section 9-5 provides that a taxable supply is made if a) the supply is for
a consideration, ii) the supply is made in the course of furtherance of an
enterprise that one carries on, iii) the supply is connected with Australia and
iv) the person making the supply is registered or required to be registered.
As for the definition of the term 'supply, section 9(10) (2) of the Australian
GST law provided a non-exhaustive list of activities or occurrences that are
included the meaning of supply. The list included supply of goods and an entry
into, or release from, an obligation i) to do anything, ii) to refrain from an
act, and iii) to tolerate an act or situation as supply. Further, much like
under the Indian law, the Australian GST law required that a supply should be
made for consideration and for this requirement to be met, there i) had to be
payment/any act or forbearance consideration for supply and ii) the said
payment/any act or forbearance or consideration is 'in connection with', 'in
response to' or 'inducement of a supply'. Therefore, there had to be any
payment/act/forbearance and the said act/payment/forbearance ought to have
sufficient nexus with the supply in question.
In the said background, the Australian Tax Office ruled that payments made on
early termination of a lease by the lessor does not constitute a supply as the
same is nothing but genuine damages for the loss suffered by the lessor. In
support of its conclusion, it observed as below:
70. Where a lease is terminated early because of the lessor exercising a right
to terminate early arising out of a default by the lessess the termination does
not occur as a consequence of any mutual agreement between the lessor and the
lessee. It is the action of the lessor in exercising the lessor's right to
terminate which brings the lease to an end.
71. The lease may require payment to be made by the lessee to the lessor to
compensate the lessor for any damage or loss suffered because of the early
termination. Genuine damage or loss cannot be characterized as a supply made by
the lessor, because the damage or loss does not in itself constitute a supply
under section 9-10.
72. A payment received to compensate the lessor for genuine damage or loss
flowing from early termination as a result of a default by the lessee is not
consideration for a supply....... There is no taxable supply because a payment
for genuine damages, which is not consideration for any earlier or current
supply, is not made in connection with any supply...........
Financial and General Print Ltd. v. Commissioner of Customs and Excise, (1995)
VAT Dec. No. 13795:- The case involved early termination of an agreement and
payment of certain damages amount by the lessee to the lessor , following the
appointment of a receiver to the lessee. Where the sum received by the lessor
was sought to be taxed on the ground that the same amounted to supply, the UK
VAT Tribunal observed as below:
In summary and looking at the entire transaction' the position is this. While
the lease is running, the lessee provides consideration in the form of rent for
the quarter and in return the lessor supplies or continues to supply possession
of the equipment. If the lessee fails to pay his quarter's rent (or commits any
other act of' default'...) the lease may be terminated and the lessor may recoup
possession. If So, the lessor's obligation to provide the service is spent and
any termination payment compensates the lessor for the latter's loss of
opportunity to provide that service
...
the lessor's termination of the lease was not a supply of services. It was
simply a unilateral act of the lessor. It terminated the lease and so terminated
all further supplies of the services of granting possession of the equipment to
the lessee ... There was no relevant service to which the compensation payment
could be directly linked. The termination cannot, therefore, be properly
described as a supply of services effected for consideration ....
39. From the terms of the agreement, is evident that there is no obligation cast
upon the Applicant to tolerate the act of breach of the contract and receive
consideration for such tolerance. Therefore, the conditions required for
invoking the levy under section 5(e) of the Schedule of the CGST Act, 2017 are
not satisfied. Accordingly, the liquidated damages claimed by the Applicant
should not be liable to GST.
Relevance and Applicability of the aforesaid decisions
40. The Indian GST law is in its formative stages. There is no jurisprudence on
certain expressions employed under the Act and taxability of damages under the
indirect tax law, particularly the GST law, is still uncertain and unclear. In
such circumstances, recourse ought to be had to international cases and rulings
understand the meaning and import of certain expressions.
41. The Supreme Court of India and High Courts across the country routinely
follow international rulings and commentaries, where there is little or almost
no jurisprudence on a given subject, for sufficient guidance. As a result, where
the rulings in aforesaid foreign rulings cited by the Applicant shed sufficient
light on the taxability of damages in the context of the expression 'tolerate an
act', such rulings ought to be taken into consideration before deciding the
issue at hand before this Authority considering the fact that the expression
examined by the foreign authorities in the decisions relied upon by the
applicant exactly the same as the expression used under the GST law.
42. The aforesaid ruling of the ATO specifically considered and decided on
taxability of damages in the context of the expression 'tolerating an act'. Such
a ruling, therefore, ought not to be disregarded without sufficient reasons for
doing so. Likewise, the decision in case of Financial and General Print Ltd
(supra) holds sufficient persuasive value and ought not to be disregarded
without providing explicit and sufficient reasons.
Mere inclusion of specific clause for payment of damages and quantification
thereof should not change the nature of transaction to transform a lawful right
of termination into an 'obligation to tolerate'
43. It is a business prudence that contracting parties foresee an act of breach
by the other party and take measures to safeguard themselves against any
consequent loss/ injury arising out of such breach. In this regard, it is a
standard practice to include specific clauses in the agreements providing
aggrieved party a right to seek damages against loss/injury. These clauses act
as a deterrence against breach of terms by the other party.
44. Mere fact that such a clause is included in the contract for protection of
the aggrieved party would not result in creation of an obligation to tolerate a
breach of the agreement. On the contrary, it gives the aggrieved party a right
to suel enforce the terms and claim damages.
45. Similarly, mere quantification of liquidated damages payable to the service
provider on termination of the Association Agreement should not, and would not,
alter the nature of transaction and transform into a supply of a service in as
much as what is paid to the service provider is nothing but damages for the
loss/injury suffered.
46. The Applicant exercised its right/entitlement to terminate the Association
Agreement on account of the service recipient's default in complying with its
obligations to make payment to the Applicant for services rendered. Due to such
default by the service recipient, the Applicant has suffered an injury/ loss.
The Indian law recognises the Applicant's right to be compensated for such
injury/ loss. To safeguard Applicant's interest under the Association Agreement,
the parties had agreed to stipulate and incorporate specified amount which shall
be payable as damages by the recipient to the Applicant. The rationale behind
insertion of a clause stipulating payment of liquidated damages is only to avoid
long-drawn litigation between contracting parties.
47. Mere mention of a clause stipulating quantum of damages payable would not in
any way alter the underlying reasons for payment of the damages, which remains
to be the injury/ loss caused to the Applicant. Had there been no mention of the
quantum of such damages, the only difference would have been that the parties
would have then approached the courts/ arbitral tribunal for determination of
the quantum of damages. The quantum adjudicated by the courts/ arbitral tribunal
would still be in respect of the injury/ loss caused. The mechanism for
determination of the damages cannot have any bearing on the nature of the
transaction. Even in the instant case, it may so happen, that the arbitral
tribunal may alter the amount of liquidated damages claimed.
48. It is submitted that, in principle, there is no qualitative difference in a
claim of liquidated damages and a claim of unliquidated damages as there would
be arbitral proceedings (in lieu of long-drawn court proceedings) between the
parties to adjudicate and assess the amount of liquidated damages payable to the
Applicant and the Applicant would still be required to adduce adequate proof of
the loss suffered as the requirement of proving the loss suffered by the
applicant is not dispensed with' by merely incorporating a clause with
liquidated damages.
49. The aforesaid argument of the Applicant has sufficient backing under Indian
law and had been constantly apperciated by Indian Courts. Amongst others, the
Supreme Court, appreciating the aforesaid aspect, observed as below in Union of
India v. Raman Iron Foundry and Ors., (1974) 2 SCC 231:
'Now it is true that the damages which are claimed are liquidated damages under
clause 14, but so far as the law in India is concerned, there is no qualitative
difference in the nature of the claim whether it be for liquidated damages or
for unliquidated damages......... It, therefore, makes no difference in the
present case that the claim of the Appellant is for liquidated damages. It
stands on the same footing as a claim for unliquidated damages. Now the law is
well settled that a claim for unliquidated damages does not give rise to a debt
until the liability is adjudicated and damages assessed by a decree or order of
a Court or other adjudicatory authority. When there is a breach of contract, the
party who commits the breach does not eo instanti incur any pecuniary
obligation, nor does the party complaining of the breach becomes entitled to a
debt due from the other party. The only right which the party aggrieved by the
breach of the contract has is the right to sue for damages. That is not an
actionable claim and this position is made amply clear by the amendment in
section 6(e) of the Transfer of Property Act, which provides that a mere right
to sue for damages cannot be transferred.
50. Based on the above, it is clear that the Applicant's right to receive
liquidated damages is not guaranteed and crystallized by a mere reference to the
payment of liquidated damages in the contract. The receipt of liquidated damages
is dependent on the finality of the proceedings before the highest appellate
forum.
51. The Applicant receives damages to make good its injury even it approaches
any court of law in ordinary course and the mere fact that the Applicant chose
to incorporate clause stipulating a genuine pre-estimate of the damages to make
goods its injury by fighting out its claim before an arbitral tribunal instead
of a court of law should not alter the nature of the transaction entered into by
the Applicant and make the damages received by it amenable to the levy of GST.
There cannot be an agreement to tolerate a breach, which is illegal as per the
terms of the Association Agreement
52. The Applicant submits an agreement to tolerate an illegal act is not a valid
agreement under the Indian law. Assuming without admitting that the Applicant is
tolerating a default by the service recipient in discharging its obligations
under the Association Agreement, it is submitted that such an agreement to
tolerate an illegal act of non-payment can have no enforceability under law.
This being so, the Association Agreement entered into by the parties cannot be
construed to cast an obligation on the Applicant to tolerate an illegal act or
situation as the same would have the effect of rendering the said agreement
unenforceable.
53. It is re-iterated that the damages claimed by the Applicant are for the
loss/injury suffered by it on account of an illegal act of the service
recipient. When the service recipient fails to pay the service provider in time
as required under the Association Agreement, the Applicant is put to irreparable
loss/injury as a result of such non-payment.
Comments on submissions made by the jurisdictional officer:
54. The jurisdictional officer had opined in its written submissions that
non-performance of a contract is an activity or transaction which is treated as
supply of service and the person is deemed to have received the consideration in
the form of liquidated damages and is accordingly required to pay tax on such
amount.
55. In this regard, the Applicant submits that mere non-performance of a
contract by the service recipient would not trigger the levy of GST on
liquidated damages paid by the service recipient. The jurisdictional officer had
not appreciated the true import of clause 5(e), which requires an agreement to
discharge an obligation to refrain from an act or tolerate an act or a
situation. The jurisdictional officer does not explain how the Association
Agreement in question is for discharge of an obligation towards refraining or
tolerating any act or a situation.
56. The Applicant submits that there is no agreement to discharge an obligation
for tolerating any act of default by the service recipient between the parties.
The payment of liquidated damages is nothing but damages for the loss suffered
by the Applicant and the same does not qualify as 'consideration' for the
purpose of GST law.
57. Unless it is demonstrated that there is an obligation under the agreement to
refrain from an act or tolerate an act or a situation and this obligation is
coupled with the presence of consideration, there can be no levy of GST. In any
event, the Applicant submits that payment of LD to the Applicant for a default
on the part of the service recipient cannot qualify as consideration for the
purpose of the levy of GST.
Time of Supply and valuation of the liquidated damages for the purpose of
payment of GST
58. Even assuming arguendo that GST is payable on liquidated damages claimed by
the Applicant, the Applicant submits that no GST is payable on liquidated
damages unless the same is actually received by the Applicant once the arbitral
award attains finality.
59. This view of the Applicant is supported by the jurisdictional officer who
observed in its written submissions to this Authority' that time of supply for
the liquidated damages may be the date on which the liquidated will be credited
in the bank account of the Applicant or the date on which Applicant shows the
receipt of liquidated damages in its books of accounts, whichever is earlier.
60. The fact that receipt of liquidated damages is uncertain is also
acknowledged by the Authority for Advance Ruling (Aar) under the erstwhile
service tax law, which had observed that it would not give a finding on an event
that has not occurred as yet and regarding which there is no certainty.
Therefore, even assuming arguendo that there would be levy of GST on the
liquidated damages due to the Applicant, it ought to be only on the actual
receipt of liquidated damages by the Applicant.
61. The jurisdictional officer has provided similar views in respect of the
valuation of the liquidated damages, observing that the value of supply of
services will be determined based on the actual receipt of the liquidated
damages by the applicant.
62. Without prejudice our submissions on applicability of GST on liquidated
damages, it is highlighted that the comment of the jurisdictional officer are in
line with the observations of the Apex Court in Union of India v. Raman Iron
Foundation and Ors., (1974) 2 SCC 231, where the Hon'ble Apex Court observed as
below:
Now it is true that the damages which are claimed are liquidated damages under
clause 14, but so far as the law in India is concerned, there is no qualitative
difference in the nature of the claim whether it be for liquidated damages or
for unliquidated damages..........It, therefore, makes no difference in the
present case that the claim of the Appellant is for liquidated damages. It
stands on the same footing as a claim for unliquidated damages. Noiv the law is
well settled that a claim for unliquidated damages does not give rise to a debt
until the liability is adjudicated and damages assessed by a decree or order of
a Court or other adjudicatory authority. When there is a breach of contract, the
party who commits the breach does not so instanti incur any pecuniary
obligation, nor does the party complaining of the breach becomes entitled to a
debt due from the other party. The only right which the party aggrieved by the
breach of the contract has is the right to sue for damages. That is not an
actionable claim and this position is made amply clear by the amendment in
section 6(e) of the Transfer of Property Act, which provides that a mere right
to sue for damages cannot be transferred.
63. In light of the above observations, it is clear that the question for time
of supply and valuation cannot arise for adjudication till the claim of
liquidated damages is finally adjudicated in the favor of the Applicant by the
highest appellate forum and the Applicant actually receives the liquidated
damages.
Statement containing the applicant's interpretation of law and/or facts, as the
case may be, in respect of the questions(s) on which advance ruling is required
Statement containing the applicant's interpretation of law and/or facts, as the
case may be, in respect of the aforesaid question(s) (i.e. applicant's view
point and submissions on issues on which the advance ruling is sought):
The position of law and our understanding of the same
28.lt is important to note various statutory provisions which have a bearing on
the questions raised for the Advance Ruling in the present Application. The
relevant statutory provisions are extracted hereunder for the ready reference of
the Hon'ble Authority :
Relevant Provisions of the Central Goods and Service Tax Act, 2017 and the
Applicant's interpretation of the same
29.Under the GST law, all supplies' of goods and services should attract GST
(unless specifically exempted). Section 9 of the Central Goods and Services Tax
Act, 2017 (CGST Act) is the charging Section which provides that there shall be
a levy of a tax called the central goods and services tax on all intra-state
supplies of goods or services or both on the value determined under section 15
of the CGST Act, 2017 at such rates not exceeding twenty percent as may be
notified by the Government. As is clear from the aforesaid Section, the key
pre-condition for the levy of GST is presence of a supply of services.
30. Section 7 of the CGST Act, 2017 defines the term supply and the relevant
portion of the same is reproduced hereunder as follows:
7. (1) For the purposes of this Act, the expression supply includes,-
(a) all forms of supply of goods or services or both such as sale, transfer,
barter, exchange, licence, rental, lease or disposal made or agreed to be made
for a consideration by a person in the course or furtherance of business;
(b) import of services for a consideration whether or not in the course or
furtherance of business;
(c) the activities specified in Schedule I, made or agreed to be made without a
consideration; and
(d) the activities to be treated as supply of goods or supply of services as
referred to in Schedule II.
(emphasis supplied)
31. Section 7 of the CGST Act, 2017 defines the term supply to include all
forms of supply of goods or services or both. Also, it expressly seeks to
include all activities treated as supply of goods or supply of services as
referred to in Schedule II of the CGST Act, 2017. In this regard, Clause 5 of
Schedule II provides for the list of activities that shall be treated as supply
of services. Inter alia, Clause 5(e) of the Act provides that agreeing to the
obligation to refrain from an act, or to tolerate an act or a situation, or to
an act shall be treated as a supply of services. The relevant portion of the
Schedule II is extracted hereunder for your ready reference:
SCHEDULE II (Section 7)
5. Supply of services
The following shall be treated as supply of services, namely:
(a) .......................
(e) agreeing to the obligation to refrain from an act, or to tolerate an act or
a situation, or to do an act; and
32. Further, although there is no comprehensive definition of the term service
(as it existed under the erstwhile service tax regime), the term service is
defined as follows under section 2(102) of the CGST Act, 2017:
services means anything other than goods, money and securities but includes
activities relating to the use of money or conversion by cash or by any other
mode, from one form, currency or denomination, to another form currency or
denomination for which a separate consideration is charged.
33. A plain reading of the aforesaid provisions indicate that for a transaction
to qualify as a supply of service', it is necessary there is an underlying
'activity performed by one person for another for consideration.
34. In order to qualify as a 'supply of service for a consideration there has to
be a service provider and a service recipient who have agreed to perform/receive
specified services. The contract/agreement should involve contractual
reciprocity.
35. For an activity to qualify as a 'service', the same has to be performed at
the behest of the service recipient. An act done without corresponding desire or
without reciprocate contractual obligation of the service recipient cannot be
considered as an activity for a consideration.
36. In the case at hand, the claims of liquidated damages are not payable as
consideration towards rendition of consulting advisory services. The claim of
liquidated damages preferred by Applicant stems from occurrence of an 'Event of
default' in terms of Section 8.1 of the Association Agreement, which includes
breach of payment obligations by SPL liuidated damages are in the nature of
compensation for losses incurred on account of termination of the contract in
other words loss of source of business/ revenue).
37. In the light of the aforesaid submissions, it is submitted that any claim
and subsequent receipt for liquidated ,damages preferred by the Applicant
against SPL should not qualify as a 'supply of service performed by one person
for another for a consideration. Accordingly, it should not qualify as supply
of service for the purpose of levy of GST.
38 It is further submitted that section 7 of the CGST Act, 2017 specifically
includes within its ambit activities which are deemed to be treated as supply of
services under Schedule II of the CGST Act, 2017. Inter alia, clause 5(e) of
Schedule II of the CGST Act, 2017 is the relevant clause for the purpose of the
instant application.
39. It is submitted that for a transaction to be covered under the list of
clause 5(e) of Schedule II as agreeing to the obligation to tolerate an act,
there has to be a concurrence to assume an obligation to refrain from an act or
tolerate an act or a situation etc. In the absence of such an obligation between
the parties, it is submitted that the said clause cannot be invoked and there
can be no levy of GST.
40. It is submitted that the claim of liquidated damages is made towards making
good the damages, losses or injuries arising from unintended' events and does
not emanate from any 'obligation' on the part of any of the parties to tolerate
an act or a situation.
41. It is submitted that suffering a damage or incurring a loss cannot be
equated or considered to be making a supply of taxable service falling within
the ambit of the above sub-clause (e) of clause 5 of Schedule II of the CGST
Act, 2017, which can possibly be invoked only when there is an 'obligation' or
'consensus' amongst the parties 'to tolerate an act or a situation.
42. In the case at hand, it is submitted that there is no obligation on part of
the Applicant to tolerate any breach of payment obligations by SPL. The
liquidated damages contemplated under the Association Agreement were
incorporated to safeguard the interest of the Applicant against an adverse
contingency which may or may not occur.
43. Considering the aforesaid factual matrix and legal position, as explained
above:
The liquidated damages claimed by the Applicant are not in lieu of any
activity/obligation which it has agreed to perform at the behest of the service
recipient. Such liquidated damages are claimable on account of breach of
contract (default in payment obligation) by SPL. The Applicant cannot be
considered to have performed any activity for a consideration for SPL with
regard to liquidated damages claimed.
Also, there is no contractual reciprocity or concurrence to assume an obligation
to refrain from an act or tolerate an act between the Applicant and SPL, which
are indispensable and essential for a transaction to qualify as a supply of
service'.
Accordingly, the transaction in question does not qualify as a 'supply of
service and hence is not subject to levy of GST.
44. In light of the above, it is clear that the liquidated damages which may be
awarded by ICC to the Applicant do not qualify as a 'supply of service for
purpose of levy of GST under the CGST Act, 2017 and would, therefore, not
attract the levy of CGST Act, 2017.
45. It is further submitted that the receipt of liquidated damages by the
Applicant would depend on the final award of the ICC which would be pronounced
only post conclusion of the arbitration proceedings on April 8, 2018.
46. It is submitted that, since the transaction would not attract GST, the
questions regarding valuation of the transaction and the point of time when the
GST liability shall be triggered do not arise.
47. The Applicant, therefore, humbly submits that, although the arbitration
proceedings will commence in the month of April 2018, the award by ICC may be
pronounced only in later part of this year or early months of next year. Hence,
even if the liquidated damages were held to be liable to GST, the question with
regard to the value exigible to GST and the time of supply can only be
ascertained once the Applicant's eligibility to receive the liquidated damages
attains finality before the appellate forum/ Court of law.
PRAYER
In the light of the above, it is prayed that the Hon'ble Authority may be
pleased to rule that:
A. Liquidated damages which may be awarded by ICC shall not qualify as 'supply
of any goods or services and hence would not be exigible to the levy of GST; and
B. Since liquidated damages are not exigible to the levy of GST, the questions
regarding valuation of supply and point of time of supply for the purpose of
levy of GST do not arise.
C. Pass any other order your good self may deem fit in the interests of justice.
03. CONTENTION - AS PER THE CONCERNED OFFICER
The submission, as reproduced verbatim, could be seen thus-
Comments and submission regarding above referred application as fallows.
Questions asked by the applicant for advance ruling
1. Whether liquidated damages that may be awarded to the applicant by
International Chamber of Commerce (ICC) qualifies as a 'supply ' under Goods and
Services Tax (GST) law, thereby attracting the levy of GST?
2. If the answer to the question No. 1 is in affirmative, what should be the
time of supply, that is to say, the point of time in which NACC's liability to
pay GST arise?
If the answer to the question No. 1 is in affirmative, what should be the value
of supply on which GST is payable, that is to say, whether the applicant is
liable to pay GST on the amount of liquidated damages claimed and awarded to the
applicant under the arbitral award or the amount which is actually received by
the applicant after conclusion of the matter before the final appellate
authority?.
Classification of service
Chapter /Section /Heading |
Description of Service |
CGST Rate (%) |
SGST/UTGST Rate (%) |
IGST Rate (%) |
Condition |
Heading 9997 |
Other services (washing, cleaning and dyeing services; beauty and physical well-being services; and other miscellaneous services including services nowhere else classified). |
9 |
9 |
18 |
- |
1. Scope of Supply :
Section 7 of the Central Goods and Services Tax Act 2017 (CGST 2017) defines
scope of supply.
As per Section 7(1) (d) the activities to be treated as a supply of good or
supply of services as referred in the sch. 2
As per schedule 2 para 5 clause (e) agreeing to the obligation to refrain from
an act, or to tolerate an act or a situation, or to do an act
As per above provision liquidated damages may be awarded to applicant NACC India
for non-performance of a contract by SPL. Non-performance of a contract is an
activity or transaction which is treated as a supply of service and the person
is deemed to have received the consideration in the form of liquidated damages,
fine or penalty and is accordingly, required to pay tax on such amount.
2. Time of Supply :
Section 13(2) of the Central Goods and Services Tax Act 2017 (CGST 2017) defines
time of supply of services shall be the earliest of the following dates.
a) The date of issue of invoice by the supplier, if the invoice is issued within
the period prescribed under sub-section (2) of section 31 or the date of receipt
of payment, whichever is earlier: or
b) the date of provision of service, if the invoice is not issued within the
period
prescribed under sub-section (2) of section 31 or the date of receipt of payment
whichever is earlier, or The date on which the recipient shows the receipt of
services in his books of account, in case where the provisions of clauses (a)
and (b) do not apply.
Prescribed time for issue of invoice:
Sec 31(2) A registered person supplying taxable services shall, before or after
the provision of service but within a prescribed period, issue a tax invoice,
showing the description, value, tax charged thereon and such other particulars
as may be prescribed.
As per Rule 47 of CGST Rules 2017 the invoice referred to in rule 46, in the
case of the taxable supply of services, invoice shall be issued within a period
of thirty days from the date of the supply of service.
NACC India issued an Invoice Dt. 23rd July 2014 for claiming Liquidated Damages
from SPL along with notice of Termination of Association Agreement after the
completion of 60 days from the date of notice of default. The issue date of
invoice is before the effective date of GST Act 2017.
As per section 13 Time of Supply may be the date on which Liquidated Damages
will be credited in the Bank account of NACC India or the date on which NACC
India will show the receipt of Liquidated damages in his books of account
whichever is earlier.
Or
As per sub-section 5 of section 13 Where it is not possible to determine the
time of supply under the provisions of subsection (2) or sub-section (3) or
sub-section (4), the time of supply shall-(a) in a case where a periodical
return has to be filed, be the date on which such return is to be filed; or (b)
in any other case, be the date on which the tax is paid. 3) Value of Supply:
As per sub-section 4 of section 15 the value of a supply of goods or services or
both shall be the transaction value, which is the price actually paid or payable
for the said supply of goods or services or both where the supplier and the
recipient of the supply are not related and the price is the sole consideration
for the supply.
Or
As per Rule 30 of CGST Rules 2017 Where the value of a supply of goods or
services or both is not determinable by any of the preceding rules of this
Chapter IV, the value shall be one hundred and ten percent of the cost of
production or manufacture or the cost of acquisition of such goods or the cost
of provision of such services.
NACC India issued an invoice Dt. 23rd July 2014 amounting 17 million USD to SPL
for liquidated damages. The decision on dispute regarding liquidated damages is
pending before ICC, London. Invoice date is before the effective date of GST Act
2017. As per Arbitration clause of Association Agreement decision of ICC, London
is final & binding remedy between the parties. In such situation value of supply
of services will be determined on the basis of actual receipt of liquidated
damages by NACC India from SPL after award of ICC, London.
04. HEARING
The case was taken up for preliminary hearing on dt. 12.06.2018, with respect to
admission or rejection of the application when Sh. N. Venkatraman Sr. Advocate
alongwith Sh. Govardhan Purohit, Advocate, Sh Amit Bhagat Advocate and Sh.
Aditya Khanna, Advocate appeared and made request for admission of ARA
application as per their written and oral submissions. They specifically point
out that they had earlier approached Service Tax Advance Ruling Authority at
Delhi and the authority had rejected their application as premature at that
time. They stated that presently also final arbitration award is awaited by
October, 2018 only. From the company's side Sh. Hans Weber Sr. Tax Director
appeared. Jurisdictional Officer, Ms. V. M. Wadkute, State Tax Officer
(PUN-VAT-C-118) Pune appeared and made written submissions.
The application was admitted and final hearing was held on 03.07.2018 , Sh. N.
Venkatraman Sr. Advocate alongwith Sh. Govardhan Purohit, Advocate, Sh Amit
Bhagat Advocate and Sh. Aditya Khanna, Advocate, Sh. Prashant Agarwal and Sh.
They appeared and made oral & written submissions. They also requested for time
to make further submissions latest by 10.07.2018 which was granted. The
jurisdictional officer, Ms. V. M. Wadkute, State Tax Officer (PUN-VAT-C-118)
Pune appeared and made written submissions.
05. OBSERVATIONS
We have perused the records on file and gone through the facts of the case and
the submissions made by the applicant and the department.
We find that the applicant M/s North american coal Corporation India Pvt.Ltd., (NACC
India) is a Private Limited Company incorporated under the Companies Act, 1956
to carry on the business of providing Technical Consultancy relating to Coal
Mining and related activities. It is a wholly owned subsidiary of M/s North
american coal Corporation, USA (NACC US).
We find that NACC, US has entered into an association agreement for mine
development and operations with M/s Sasan Power Ltd. (SPL or Reliance) a company
which is a part of Reliance Anil Dhirubhai Ambani Group which is in the business
of developing, designing, operating, maintaining owning an Ultra Mega Power
Project in Sasan, Madhya Pradesh, India. The Association Agreement as referred
above is effective from 1st January, 2009 in order to provide technical know how
to SPL in relation to mine development and operations.
We further find that later on in March, 2011, NACC, US incorporated a
subsidiary, NACC, India and the rights and obligations of NACC, US as per the
original Association Agreement were transferred and assigned to the applicant
with the consent of SPL.
The Sasan Project as per the Association Agreement was divided into three phases
being, (1) Predevelopment phase, (2) Development phase and (3) Production phase.
The details of terms and conditions of the agreement during these phases are as
mentioned at relevant places in the Applicant's submission above.
We find that NACC, US in the initial phase and later NACC, India had rendered
significant services to SPL as per terms and conditions of Association Agreement
referred above. However it is alleged by the applicant that after some time SPL
curtailed the activities of the applicant and engaged its Inhouse Consultants.
The applicant further states that the last invoice against which, payment was
made by SPL to the applicant pertained to the period up to September, 2013 and
it stopped making payment against invoices of the applicant pertaining to
services performed after the period 1st October, 2013.
The applicant further stated that they were constrained to terminate the
Association Agreement with SPL as per the relevant articles of the Association
Agreement.
The applicant states that several suits and counter suits were filed by the
applicant and SPL against each other and it was finally ordered by the Hon'ble
Supreme Court that the parties could participate in arbitration proceedings
outside India despite being companies incorporated under the Companies Act,
1956, in India. The applicant further stated that accordingly the applicant and
SPL have initiated arbitration proceedings before the International Chamber of
Commerce (ICC) which are pending finalization.
We find that in view of the above details, the applicant has raised three
questions for decision of this authority which are as under:-
1. Whether liquidated damages that may be awarded to the Applicant by the
International Chamber of Commerce (ICC) qualifies as a 'supply' under the
Goods and Services Tax (GST) law, thereby attracting the levy of GST ?
2. If the answer to Question No. 1 is in the affirmative, what should be the
time of supply, that is to say, the point of time in which NACC's liability to
pay GST arises ?
4. If the answer to Question No. 1 is in the affirmative, what should be the
value of supply on which GST is payable, that is to say, whether the Applicant
is liable to pay GST on amount of liquidated damages claimed and awarded to the
Applicant under the arbitral award or the amount which is actually received by
the Applicant after conclusion of the matter before the final Appellate
authority.
We find that in respect of the above, the applicant in their oral and written
submissions with regard to their interpretation of the issue have made
contentions as under:-
(I) Firstly they have contended that their obligations under the Association
Agreement do not constitute as supply of services. They contended that the claim
of liquidated damages does not qualify as a 'service' itself as it lacks the
element of reciprocating which forms the sine qua non for a transaction to
qualify as a service.
(II) Secondly they have contended that even if one were to argue that the claim
of liquidated damages amounts to a service such claim cannot be regarded as
being in course or furtherance of business. The termination of the Association
Agreement puts an end to the business relationship of the applicant with the
service recipient. It results in complete and absolute cessation of the business
of the applicant and not its furtherance. That the act of termination cannot be
called in course of any business as the usage of the term 'in course' indicates
continuity' of an activity.
(III) Thirdly they have contended that the situation in view of the facts of the
present case would not get covered under clause 5 (e) of Schedule II of the CGST
Act, as there is no obligation to refrain from an act or to tolerate an act or a
situation or to do an act.
(IV) Fourthly, they have contended that liquidated damages received for
breach/termination of a contract cannot qualify as consideration, stating that
liquidated damages paid by the service recipient is neither in respect of nor in
response to any supply made by the applicant, instead it is paid to make good,
loss/injury suffered by the applicant as a result of premature termination of
the Association Agreement.
(V) They stated that mere inclusion of specific clause for payment of damages
and quantification thereof should not change the nature of transaction to
transform a lawful right of termination into an 'obligation to tolerate'.
We find that the applicant has referred to various case laws in support of their
above contentions which are given in detail in the submissions and contentions
portion of their application referred above.
We find that in view of the above detailed facts and contentions of the case, we
need to examine the issue at hand as under:-
We find that as per Section 9(1) of the CGST Act regarding levy and collection
Section 9(1) --- Subject to the provisions of sub-section 2 there shall be
levied a tax called the Central Goods and Services Tax on all Intrastate
supplies of goods or services or both except on the supply of Alcoholic Liquor
for human consumption, on the value determined under Section 15, at such rates
not exceeding twenty percent, as may be notified by the Government on the
recommendations of the Council and collected in such manner as may be prescribed
and shall be paid by taxable person.
From the above we find that CGST is leviable on Intra-State supplies of goods or
services or both.
We find that Section 7 of the CGST Act gives scope of 'supply'.
Section 7 of the CGST Act reads as under:-
7. (1) For the purposes of this Act, the expression supply includes-
(a) all forms of supply of goods or services or both such as sale, transfer,
barter, exchange, licence, rental, lease or disposal made or agreed to be made
for a consideration by a person in the course or furtherance of business;
(b) import of services for a consideration whether or not in the course or
furtherance of business;
(c) the activities specified in Schedule I, made or agreed to be made without a
consideration; and
(d) the activities to be treated as supply of goods or supply of services as
referred to in Schedule II.
(2) Notwithstanding anything contained in sub-section (1),--
(a) activities or transactions specified in Schedule III; or
(b) such activities or transactions undertaken by the Central Government, a
State Government or any local authority in which they are engaged as public
authorities, as may be notified by the Government on the recommendations of the
Council, shall be treated neither as a supply of goods nor a supply of services.
(3) Subject to the provisions of sub-sections (1) and (2), the Government may,
on the recommendations of the Council, specify, by notification, the
transactions that are to be treated as -
(a) a supply of goods and not as a supply of services; or
(b) a supply of services and not as a supply of goods.
We find that Section 7(1) provides that for the purposes of this Act, the
expression 'supply' includes:
(a) all forms of supply of goods or services or both such as sale, transfer,
barter, exchange, licence, rental, lease or disposal made or agreed to be made
for a consideration by a person in the course or furtherance of business;
(b) import of services for a consideration whether or not in the course or
furtherance of business;
(c) the activities specified in Schedule I, made or agreed to be made without a
consideration; and the
(d) activities to be treated as supply of goods or supply of services as
referred to in Schedule.
Where the word 'include' is of specific importance which implies that all the
activities that are given in Section 7 (1) (a), (b), (c), and (d) would be
included in 'supply'. For the purposes of this Act which implies that otherwise
than the scope as covered in this Section and Act, the word 'supply' may even
have a broader connotation and scope.
Thus as per the scope of the word 'supply' in the Act and the present facts of
the case, we find that supply includes:-
(6) all forms of supply of goods or services or both such as sale, transfer,
barter, exchange, licence, rental, lease or disposal
(i) made or agreed to be made for a consideration by a person
(ii) in the course or furtherance of business.
Apart from the above provisions we also need to refer to Sr. No. 5(e) of
Schedule II as given in Section 7(1)(d) of the CGST Act which is regarding the
activities to be treated as supply of goods or supply of services. We find that
Sr. No. 5(e) of Schedule II states that the following shall be treated as supply
of services, namely:-
(e) Agreeing to the obligation to refrain from an Act or to tolerate an Act or a
situation or to do an act.
Thus in view of the provisions as above we are required to examine the facts of
the present case and details of the Association Agreement as submitted, to
ascertain whether tax liability would be there or not on the applicant in
context of detailed transactions/acts presented before us.
We find that first of all there was an Association Agreement first between NACC,
US and SPL with effect from 1st January, 2009 and with effect from March, 2011,
the rights and obligations of NACC, US as per the original Association Agreement
were transferred and assigned to the applicant with the consent of SPL and we
clearly find that this agreement was in respect of providing technical knowhow
to SPL in relation to mine development and operations. We find that as per the
Association Agreement referred above, the provision of services in the Sasan
project was to be carried out in three phases as per agreed terms and conditions
of payment and services provided and referred as under:-
(i) Pre-development phase.
(ii) Development phase.
(iii) Production phase.
We find that there is no dispute with respect to provision of services and
applicability of levy of taxes in respect of the above services provided between
the applicant and the service recipient SPL as it clearly falls within the scope
of supply as given in Section 7(1)(a) of the CGST Act.
However we find that the Association Agreement as referred above did not last
for the whole period as envisaged in the Association Agreement and the agreement
is claimed to be terminated for breaches on the part of the service recipient
SPL by the applicant in view of the existent provisions as were already there in
the Association Agreement entered into between the applicant and SPL.
Now we refer to the relevant clauses in respect of termination of the agreement
that were included in it as per the mutual agreement as per terms given in
Association Agreement between the applicant and SPL. We find that Article VI of
the Association Agreement as referred above provides for term and termination
which is as under:-
ARTICLE VI
TERM AND TERMINATION
Section 6.1 Term. Under earlier terminated in accordance with Section 6.2, the
term of this Agreement shall commence on the Effective Date an shall continue
until the end of the Production Phase (the Initial Term). Following the
Initial Term, the parties may extend this Agreement by written agreement for any
number of one (1) year terms (each, an Extended Term and, together with the
Initial Term, the Term) until the Agreement is terminated pursuant to Section
6.2.
Section 6.2 Termination. This Agreement may be terminated :
a) At any time by mutual agreement of the parties;
b) By either parties in accordance with Article VII (Force Majeure); or
c) By either parties in accordance with Article VIII (Events of Default).
Section 6.3 Effect of Termination
(a) Upon termination of this Agreement for any reason, NAC shall furnish to
Reliance (a) within sixty (60) days after the effective date of termination, an
initial invoice for settlement of all costs incurred prior to the termination
date and (b) within twenty (20) days of incurring such costs, additional
invoices for (i) the On-Site Costs incurred as a result of the repatriation of
the On-Site Consultants and (ii) the On-Site Costs relating to the
tax-equalization payments for the On-Site Consultants. Reliance's payments of
such invoices shall be subject to the provisions of Sections 5.3 and 5.6.
(b) If Reliance terminates this Agreement pursuant to Section 6.2(c), any
damages recoverable by Reliance shall be limited to the amount of the
Development Fees and/or Production Phase Royalties actually paid by Reliance
during the year in which Reliance terminates this Agreement pursuant to Section
6.2(c), in no event to exceed U.S. $1,000,000 in the aggregate.
(c) If NAC terminates this Agreement pursuant to Section 6.2(c), Reliance shall
pay to NAC, as liquidated damages and not as a penalty or other punitive amount,
the amount specified below:
If Termination Occurs During: Then the Termination Payment is U.S.: Year 1 of
the Development Phase $17 million Year 2 of the Development Phase $13 million
Year 3 of the Development Phase $15 million Year 4 or later of the Development
$17 million Phase Any year in the production phase $17 million, less the
aggregate amount of the Production Phase Royalties received by NAC prior to the
termination date
ARTICLE VIII
EVENTS OF DEFAULT
Section 8.1 Default by Reliance. If Reliance shall at any time be in breach of
its (a) payment obligations, (b) other obligations pursuant to this Agreement,
including failure to provide reasonable access to the Mine, the Preparation
Plant or any o Mining Project that are relevant to the duties and obligations of
NAC hereunder and the failure to timely provide presentations in Section 13.2
(1, NAC may give written notice of such default to Reliance, in which
caseReliance shall have twenty-one (21) days within which to cure the default.
If, at the end of the twenty-one (21) day period, Reliance has not cuired the
default NAC shall have the right, (i) if the default is of the type described in
subclause (a) above, to immediately cease providing the Services until such time
as the event of default is cured, (ii) if the default is of the type described
in subclause (b) above, to cease providing such Services as NAC determines, in
its reasonable discretion, cannot be performed due to Reliance's default until
such time as the event of default is cured, or (iii) if any such default is not
cured within sixty (60) days and NAC is not then in breach of this Agreement, to
terminate this Agreement. Reliance shall continue to be responsible for the
On-Site Costs during the period of the default and prior to the termination of
the Agreement.
Section 8.2 Default by NAC. If NAC shall at any time be in breach of its
obligation to provide Services hereunder, Reliance may give written notice of
such default to NAC, in which case NAC shall have ten (10) days within which to
cure the default. If, at the end of the ten (10) day period, NAC has not cured
the default Reliance shall have the right (i) to cease reimbursing NAC for
services not actually provided until such time as the event of default is cured
or (ii) if the default is not cuired within sixty (60) days and Reliance is not
then in breach of this Agreement, to terminate this Agreement. Reliance shall
not be responsible for the On-Site Costs during the period of default and prior
to the termination of this Agreement, other than the repatriation and tax
equalization costs identified in Annex C and, if any, on the On-Site Consultants
Schedule
Further, in view of default as above we find that Article XII of the Association
Agreement clearly provides for Governing law and dispute resolutions as under:-
Section 12.1 - Governing Law : This agreement shall be governed by, and
construed and interpreted in accordance with, the laws of the United Kingdom
with regard to its conflicts of laws principles
Section 12.2 Dispute Resolution: Arbitration
(a) Any and all claims, disputes, questions or controversies involving Reliance
on the one hand and NAC on the other hand arising out of or in connection with
this Agreement (collectively, Disputes) which cannot be finally resolved by
such parties within 60 (sixty) days of arising by amicable negotiation shall be
resolved by final and binding arbitration to be administered by the
International Chamber of Commerce (the ICC) in accordance with its commercial
arbitration rules then in effect (the Rules). .The place of arbitration shall
be London, England. Each party shall appoint one (1) arbitrator and the two (2)
arbitrators so appointed shall together select and appoint a third arbitrator.
If either Reliance, on the one hand, or NAC, on the other hand, fail to appoint
their respective arbitrator within thirty (30) days after receipt by
respondent(s) of the demand for arbitration or if the two 2) party-appointed
arbitrators are unable to appoint the chairperson of the arbitral tribunal
within thirty (30) days of the appointment of the second arbitrator, then the
ICC shall appoint such arbitrator or the chairperson, as the case may be, in
accordance with the listing, ranking and striking provisions of the rules. Save
and except the provision under Section 9, the provisions of the Part 1 of
(Indian) Arbitration and Conciliation Act, 1996, as amended (the Arbitration
Act) shall not apply to the arbitrations. The arbitrators shall not award
punitive, exemplary, multiple or consequential damages. In connection with the
arbitration proceedings, the parties hereby agree to cooperate in good faith
with each other and the arbitral tribunal and to use the respective best efforts
to respond promptly to any reasonable discovery demand made by such party and
the arbitral tribunal.
(b) Arbitration proceedings shall be conducted in the English language and the
arbitral award (the Award) shall be rendered be latest than six (6) months
from the commencement of the arbitration or as otherwise provided by the Rules,
unless otherwise extended by the arbitral tribunal for no more than an
additional six (6) months for reasons that are just and equitable.
(c) Except as otherwise required by Applicable Laws of India, the arbitration
proceedings and the Award shall not be made public without the joint consent of
each party and each party shall maintain the confidentiality of such proceedings
and the Award.
(d) Each party shall bear its own arbitration expenses and Reliance on the one
hand, and NAC, on the other hand, shall pay one-half of the ICC's and the
chairperson's fees and expenses, unless the arbitrators determine that it would
be equitable if all or a portion of the prevailing party's expenses should be
borne by the other party. Unless the Award provides for nonmonetary remedies,
any such Award shall be made and shall be promptly payable in (i) U.S. Dollars
if payable to NAC or (ii) Rupees if paid to Reliance net of any tax or other
deduction. The Award shall include interest from the date of any breach or other
violation of this Agreement and the rate of such interest shall be specified by
the arbitral tribunal and shall be calculated from the date of any such breach
or other violation to the date when the Award is paid in full.
(e) All notices and other communications by any party to the other party or by
the arbitral tribunal to any disputing party in connection with the arbitration
hereunder shall be in accordance with the provisions of Section 14.1.
(f) Each of the Parties expressly understands and agrees that the Award shall be
the final and binding remedy between them regarding any and all Disputes
presented to the arbitral tribunal.
Thus we find clearly from the terms and conditions as referred above in respect
of Article VI, Article VIII, and Article XII of the Association Agreement as
refereed above that as per the terms and conditions of the agreement referred
above there was clearly an agreement between the applicant and SPL to tolerate
an act or situation in case such act was done by the other or such a situation
arose because of default on part of one or the other during the course of the
project covered under the Association agreement and in case of default of terms
of the agreement by one of the parties to this Association Agreement, the
defaulting party was required to compensate the other party as per the terms and
conditions of the Agreement. However we find that if there was further dispute
in respect of the claims to be recovered/received by the one party from the
other in view of violations or termination of the Agreement then they could
approach the ICC for arbitration on the issue and to receive suitable amounts as
claims cum consideration in view of the violations on the part of the party
violating or defaulting on the Association Agreement.
Further as per the Association Agreement presented before the Authority it is
very clear that the amount or consideration to be received by one party i.e. the
applicant if any after arbitration from the defaulting party are suitable
compensation only for tolerating the act of default or situation of default by
one party on the part of the other party as per the terms and conditions of the
Association Agreement and are not liquidated damages as claimed by the applicant
as would be clear from the specific mentioned under Section 12.2 Dispute
Resolution: Arbitration which clearly states as under:-
The Arbitrators shall not award punitive, exemplary, multiple or consequential
damages
Thus we find that the consideration if any as received by the applicant after
arbitration by the ICC would clearly qualify as 'supply' as per Sr. No. 5(e) of
Schedule II of the CGST Act which reads as under:-
(5) Supply of Services : The following shall be treated as supply of services:-
(e) Agreeing to the obligation to refrain from an act or to tolerate an act or
a situation or to do an act.
In the present case as per details presented before us, we clearly find that
there is a clear understanding or agreement between the parties in the present
case to foresee and tolerate an act or a situation of default on the part of
either of them for a monetary consideration which is actually a consideration
received by them, though in the agreement they may be giving this consideration,
other names such as 'damages' or 'compensation' as thought proper by them, but
these different nomenclatures in their Agreement would in no way change the
actual nature of monetary consideration which would clearly be taxable for the
supply of services as per Sr. No. 5(e) of Schedule II of the CGST Act, 2018.
Further we find that the case laws relied upon by them are not relevant in
respect of the present facts of the case and Association Agreement as submitted
in respect of the present case and therefore cannot be considered.
Now we take one by one the questions posed by the applicant before this
authority
1. Whether liquidated damages that may be awarded to the Applicant by the
International Chamber of Commerce (ICC) qualifies as a supply under the
Goods and Services Tax (GST) law, thereby attracting the levy of GST ?
Answer The consideration that may be awarded to the applicant by the ICC would
qualify as supply of service as per Section 5(e) of Schedule II of Section 7(1)
of the CGST Act as per detailed discussions above in this regard.
2. If the answer to Question No. 1 is in the affirmative, what should be the
time of supply, that is to say, the point of time in which NACCs liability to
pay GST arises ?
Answer The provisions of Section 13 of the CGST ACT will determine the time of
supply in cases of supply of services. In the subject case the liability of tax
would arise on the applicant as per Sr.No.5(e) of Schedule II of Section 7(1) of
the CGST Act and the time of supply would be determined as per the provisions of
Section 13 of the CGST Act after the award of arbitration proceedings is given
by the Arbitration Tribunal as administered by the ICC as per the Association
Agreement by the parties to dispute, in the present proceedings.
3. If the answer to Question No. 1 is in the affirmative, what should be the
value of supply on which GST is payable, that is to say, whether the Applicant
is liable to pay GST on amount of liquidated damages claimed and awarded to the
Applicant under the arbitral award or the amount which is actually received by
the Applicant after conclusion of the matter before the final Appellate
authority.
Answer : In view of the facts presented before us, the value of supply of
services will be actual liquidated damages cum consideration as decided and
pronounced in the award administered by ICC.
06. In view of the extensive deliberations as held hereinabove, we pass an order
as follows :
ORDER
(under section 98 of the Central Goods and Services Tax Act, 2017 and the
Maharashtra Goods and Services Tax Act, 2017)
NO.GST-ARA- 07/2018-19/B- 63
Mumbai, dt. 11/07/2018
For reasons as discussed in the
body of the order, the questions are answered thus -
1. Whether liquidated damages that may he awarded to the Applicant by the
International Chamber of Commerce (ICC) qualifies as a supply under the
Goods and Services Tax (GST) law, thereby attracting the levy of GST ?
Answer : Answered in the affirmative.
2. If the answer to Question No. 1 is in the affirmative, what should be the
time of supply, that is to say, the point of time in which NACCs liability to
pay GST arises ?
Answer: The time of supply would be determined as per the provisions of Section
13 of the CGST Act after the award of arbitration proceedings is given by the
Arbitration Tribunal as administered by the ICC as per the Association Agreement
by the parties to dispute, in the present proceedings.
3. If the answer to Question No. 1 is in the affirmative, what should be the
value of supply on which GST is payable , that is to say, whether the Applicant
is liable to pay GST on amount of liquidated damages claimed and awarded to the
Applicant under the arbitral award or the amount which is actually received by
the Applicant after conclusion of the matter before the final Appellate
authority.
Answer : The value of supply will be the actual amount of damages received by
the applicant from SPL after the award by ICC
Place:- Mumbai
Date : July 11, 2018
-sd-
SHRI B.V. BORHADE
(MEMBER)
-sd-
SHRI PANKAJ KUMAR
(MEMBER)
Copy to:
1. The applicant
2. The concerned Central / State officer
3. The Commissioner of State Tax, Maharashtra State, Mumbai
4. The Commissioner of Central Tax, Churchgate Mumbai
Note :- An Appeal against this advance ruling order shall be made before The Maharashtra Appellate Authority for Advance Ruling for Goods and Services Tax, 15th floor, Air India building, Nariman Point, Mumbai - 400021.
Equivalent .